Perform Project MRP
Explanation
This activity is used to perform project material requirements planning with a single 
project (project MRP) or with multiple projects (multiproject MRP). The application creates 
project MRP planned 
orders and offers suggestions for planning orders for optimal manufacturing, 
considering material availability. 
Part requirements can be ascertained based on the 
sources of supply and demand such as shop orders or customer orders. If project MRP was 
performed previously, then all the planned supplies and action messages 
generated in the previous process will be removed first. The results of project MRP 
suggest a process for fulfilling the demands using, for example, purchase or 
shop order requisitions. These results also suggest how to plan orders for 
optimal manufacturing in view of material availability. Project MRP plans the supply 
for all the parts with a dependent demand. The product or recipe structures of 
the parts must have been entered. After the structures are entered, you can run 
project MRP for all the parts with a dependent demand. Project MRP considers only 
company-owned stock and activity specific requirements. Planning methods 
B, C, N, O, and T are excluded by project MRP. 
Prerequisites
	- Project MRP identifies supply and demand for project MRP parts generated in 
the following IFS modules: IFS/Customer Order, IFS/Purchasing, IFS/Project 
	Master Scheduling, IFS/Shop 
Order and IFS/Work Order only if those demands are tagged with PPSA. 
- To perform multiproject MRP, a planned
      netting group must have been defined in IFS/Project. 
Project MRP requires the following general prerequisites:
	- Bill of Materials (BOM) must have been defined 
for the parts, and lead times for both purchased and manufactured 
parts must have been established. The product structures must be in the Plannable 
or Buildable status, otherwise the BOM explosion
 will stop. Project MRP 
only uses the existing product structure with the alternate indicated by an 
	asterisk
	(*).
- Project MRP calculation will consider inventory parts
      that have the MRP Control flag check box selected on the 
	Inventory 
	Part/Manufacturing tab.
- Before you can run project MRP, you must go through an 
extensive set up in the IFS/Inventory and IFS/Purchasing modules in IFS 
Distribution. You must create calendars and attach them to the sites. You must 
have entered basic data in IFS Manufacturing and the IFS/Shop Order. 
Since project MRP is based on the quantity on hand and planned orders, data must be 
	available in these components.
- In addition to the basic requirements for project MRP as discussed above, customer orders, shop orders, and purchase orders for these 
parts need to exist. There is much additional information that affects project MRP, and 
it is important that you verify this information and its accuracy before running 
any calculations. 
- Inventory parts with the DOP supply code are managed within DOP.
- Project MRP calculation will consider inventory parts with a part
 that allows demand and supply.
- PPSA must be in the Released status.
System Effects
	- A new background job for the project MRP process will be started, and it can be queried for in the 
	Background Jobs window.
- After the process is executed, it can get the Error, Warning,
      or Ready status.
  
    | Status | Significance | 
  
    | Error | Some critical errors 
	have occurred. Project MRP stops the process. | 
  
    | Warning | A message posted for 
	this process has to be reviewed by the user. This can be done by right-clicking and
      then clicking View Detail in the 
	Background 
	Jobs window, which displays the posted message in the status 
	information table. If the user decides to continue
      the project MRP process when an error occurs, the system will post a message
      containing a warning. | 
  
    | Ready | The process completed successfully without 
	any errors. | 
	- The project MRP will generate shop order requisitions for the 
	parts that must be manufactured and purchase requisitions for parts that 
	must be purchased. Shop order requisition type and purchase requisition IDs 
	are projectt MRP. Shop order 
      requisitions that are not converted to shop orders will be 
	deleted in the next project MRP process.
- The project MRP will calculate the lowest level code parts
      and update the Low Level field on the 
	Inventory Part/Manufacturing 
	tab.
- In the multiproject MRP process, when a user specifies a
      planned netting group (PNG), the system creates a project MRP planned material
      transfer requisition (MTR). The multiproject MRP process creates material transfer
      requisitions in 
	addition to shop requisitions and purchase requisitions. MTRs created by the
      multiproject MRP will not have the MTR Manually Created check box selected.
- When creating MTR, the Generate MTR for Planning Only 
check box in the
Planned Netting Group window determines the type 
of MTR that will be created by project MRP. If the check box selected, project MRP will create 
MTR with the Planning type. If it is not selected, possible MTR types that 
will be created are: Transfer, Borrow and Payback.
- If the Generate Safety Stock check box is selected in
	Project 
Navigator/Activity List, Project 
Navigator/Activity, 
	Activity/General or 
	Activities window, and if the part 
has safety stock specified in the 
	Inventory
	Part/Planning 
Data tab, then safety stock will be generated for this part and activity 
when running project MRP.
Window
Perform Project MRP 
per Activity
Perform Project MRP 
per Project PNG
Perform Project MRP 
per PNG
Related Window Descriptions
Perform Project MRP per Activity
Perform Project MRP per Project PNG
Perform Project MRP per Planned Netting Group
Procedure
	- Open the Perform Project MRP per Activity, 
	Perform Project MRP per Project PNG or
	Perform Project MRP per PNG dialog box depending on 
	the way you want to perform project MRP.
- Your default site appears in the 
	Site field. Enter the site for which 
	you want to run project MRP.
    Use the List of Values to select from the available sites. Entering a value in 
	this field is required. 
- In the Project ID 
	field, enter the 
	ID of the project for which you want to run project MRP. 
	(If 
	you enter the wild card (%) or leave the field blank, project MRP is run for all 
	open projects under the specified site).
- 
	In the Planned Netting Group field, enter the ID of the PNG for which you want 
	to run project MRP. (If you enter the wild card (%),
    the system will process all PNGs belonging to the specified site). 
- In the Run Date 
	field, enter the date on which you want to run project MRP. The 
	current date is used by default. 
- If you want to stop the 
	project MRP process if an 
	error occurs, select the Stop PMRP on Error check box.
- If you want to add a 
	day's lead-time back off to
    the planned receipts, select the Add 1 day Lead Time check box. 
	
- 
	If you want to create messages for phantom part 
	dependent demands, select the Phantom Part Dependent 
	Demand check box.
- If you want the 
	project MRP process to create safety stock replenishment orders on 
	the project MRP run date, select the Plan Safety Stock Receipt on PMRP run Date 
	check box. If it is not selected, safety stock replenishment orders will be 
	created on the event date itself.
- If you 
	want to 
	exclude PPSAs defined in any PNG when performing project MRP (not 
	multiproject MRP) and 
	when using the 
	Perform 
	Project MRP per Activity dialog box, you have the option of selecting the
	Exclude PPSAs grouped under any 
	PNG check box. 
- If you want to start MRP after 
	project MRP is completed, 
	select the Start MRP Process once PMRP is completed check box.
- If you 
	want MRP to include alternate components in the planning calculation, select 
	the Plan Alternate Component check box. This will be enabled only 
	after selecting the Start MRP process once PMRP is completed check 
	box.
- Click 
	OK.