Change Purchase Order Change Order Back to Planned
Explanation
When the purchase order change order has been released, it is no longer 
possible to register any changes to the header or lines. If you need to make any 
further changes to the change order you will need to demote the purchase order 
change order back to the Planned status. Then when the new changes are registered you can proceed in the workflow by releasing the change order 
once again.
Prerequisites
	- A purchase order change order must exist in the Released or 
	Authorized status.
System Effects
	- The status of the purchase order change order is updated to Planned 
and it will be possible to register further changes to the change order. (Note 
that this status is not the same as the purchase order status).
- If purchase authorization is used for the purchase order change order, the 
authorization rule and routing will be removed from the change order.
Window
Purchase Order Change Order
Related Window Descriptions
Purchase Order Change Order
Procedure
	- Open the Purchase Order Change Order window and query for 
	the desired purchase order change order.
- Right-click and then select Change to Planned.
- Click OK to confirm. The change order is demoted to the Planned 
	status.