Connect Purchase Requisition Line to Project Activity
Explanation
This activity is used to manually connect a purchase
requisition line to a project activity from the purchase requisition line
itself. This activity is performed to obtain the cost of the project activity of
goods being requested for the project
through the purchase requisition.
Note that you can manually connect an existing
purchase requisition line to a project activity also from the project activity. (Refer
to the activity Connect Existing Object to Activity). Another alternative
is to handle a project demand by procuring material against the miscellaneous
demand (on the project activity): In such situations, the connection between the
project activity and the purchase requisition line would be generated by the system.
Of the above alternatives, manually connecting a
purchase requisition line to a project activity from the line itself (described
in this activity), is the most efficient process of handling
purchase requisitions for a project activity. This is because it excludes the
need to access the project client when handling project supplies. If you
have a demand against inventory for a project activity, you can supply this by
creating a purchase requisition for that demand in a standard manner, and connecting it to a project activity from the purchase requisition line itself.
 
Note: A purchase requisition line that has been
connected to a project, can result in the creation of a purchase order line or a
request for quotation (RFQ), and the request for quotation may in turn be
converted to a purchase order line. In both cases, the purchase order line that
is created will also inherit the connection to the project activity as well as the
pre-posting.
Prerequisites
  - The purchase requisition line must not have the PO Created or Request
    Created status.
- The purchase requisition line must not have been
    connected to a project activity.
- The project to be connected must be in the Approved or
    Started status.
- The project activity must be in the Planned or Released status to
    be available.
- The demand code on the purchase requisition line
    must be either Inventory Order or Non-Inventory Order.
- The purchase requisition line should not have any
    exchange components.
- The site of the purchase requisition line must have been
    defined as an allowed site for the connected project.
- The relevant posting type must have been specified
    for the project code part.
- The project code part must not have been pre-posted with a financial
    project.. 
- Project manual connections to the purchase requisition
    lines must have been made available on the Project Details/Project Manual
    Connections tab.
System Effects
As a result of this activity:
  - The purchase requisition line will be connected to the
    project activity. 
- The purchase requisition line will display details
    about the project activity to which the line has been connected.
- The purchase requisition line will get a project pre-posting. (As the 
  purchase requisition line already exists, it may already have pre-postings. If 
  pre-posting on the code part already exists, they will be replaced by the 
  project pre-posting. If the project pre-posting has no value for a code part 
  then the existing pre-posting on the object will remain unchanged. Also the 
  project and activity sequence will be posted.) 
- The Project Info/Connections tab and
    the Project Details/Supply/Pur Req Line tab will
    display details of the purchase requisition line connected to the project
    activity.
Window
Purchase
Requisition
Related Window Descriptions
Purchase Requisition
 Connect to Activity
Procedure
  - Open the Purchase Requisition window,
    and query for the relevant purchase requisition.
- Select the required purchase requisition line, right-click, point to
     Project Connections and then click  Connect to Activity. The 
	Connect to
    Activity dialog box opens. 
-  To select the activity to which you want
    to connect the purchase requisition line, click on the  Program ID field
    (or the Project ID  field if your project does not have a program ID).
- Click List, and use the List
    of Values, to select the program ID pertaining to the activity you want to select.
- You can continue to specify the
    criteria for the activity you want to select, by clicking on the  Project
    ID, 
    Sub Project ID, and  Activity ID fields, and then selecting a
    value from the List of Values.
- Alternatively, you can enter the activity sequence in
    the Activity Sequence field, or select it from the List of Values. (The activity sequence
    can be obtained from the Project Info/Activity/Details tab.) 
- Click OK to save the record.