Enter Components to Send to Supplier
Explanation
 
When outsourcing you have to send the material to your supplier, which is 
needed to either manufacture or to pack the parts that you in turn will 
purchase.
 When entering the purchase order line, any components entered in
a product structure in IFS/Manufacturing Standards is copied to the purchase
order line. In case a product structure is not used, you can manually specify
the components. These parts will be sent to the supplier
with each purchase order. 
You should also reserve the material in inventory if it is not automatically
done by the system.
This function does not allow you to charge, i.e., sell
the material or the components to your supplier. Therefore, when the material is
sent to the supplier it is always considered as work in progress and accounted
as such. 
Depending on the requirements or practices of your industry, instead of 
sending the component parts with each purchase order, you can backflush them. 
Backflushing involves transporting the component material to a special 
backflushing location in advance, and automatically issuing the components as 
and when the purchase parts (top parts) are received from the supplier. There is 
no need for reservation or picking, as the components are to be directly issued.
 
In case a product structure is not used (or when you
have manually entered a component line), you must select the Backflush check box and
specify a backflushing location in the Supplier Material for Purchase Order Line
window. Otherwise these values would be used by default for every product 
structure, in IFS/Manufacturing Standards. Note that backflushing is enabled per 
component line; therefore you could choose to backflush some components and send 
the other components through the normal supplier material flow.
 
Prerequisites
  - The purchase order line must have been
    entered and saved.
  
- Prior to reserving the material, you have to
    enter it and indicate the quantity.
  
-  The Purchased Component Method field on the
	Site/Sales and 
	Procurement tab should be set to Supplier Material for the 
	system to enable issuing component parts using the 
	Supplier Material for Purchase Order Line window.
System Effects
  - The component parts will be connected to the purchase
order. The material will be reserved in inventory after performing the
reservation.
- If you had chosen to backflush, the automatic issuing of component parts 
	from the backflushing location will be enabled. This is a direct issue to 
	the supplier, and will take place as and when purchase parts and top parts 
	are received (at purchase order receipt).
 
Window
Supplier Material for Purchase Order Line
Related Window Descriptions
Supplier Material for PO Line
Purchase Order 
Purchase
Order/Part Order Lines
Procedure
In the Supplier Material for Purchase Order Line window:
  - Query for the purchase order to which you want to connect the component parts.
  
- Click New.
  
- In the  Component Part  field, specify the component
    part (the inventory part) that will be connected to the purchase. Either
    enter the code for the sales part or select it from the List of
    Values. If applicable, you can indicate a condition
    code in the Condition Code field.
  
- Enter the date on which the supplier needs the component
    parts. 
  
- In the  Qty per Assembly  field, specify how many
    component parts are needed to manufacture or pack each purchase part.
  
- To issue components using backflushing, select the Backflush
    check box. Also specify a desired picking location as the backflushing location
    in the Backflush
    Location field.
  
- In the Supply Code  field, select either
    Inventory Order or Project Inventory. 
 (The Project Inventory supply code is allowed only for purchase order lines
    that are connected to project activities. In such cases, parts can be
    reserved and picked only from the project inventory of the connected
    project)
- Save when completed.
  
- Repeat steps 3—9 until all the component parts are
    entered. Then close the 
	Supplier Material for
    Purchase Order Line window.
  
In the Purchase Order window:
  - Query for the purchase order to which you want to
    connect the component parts.
  
- On the Part Order Lines
    tab, select the desired purchase order line and choose  Supplier Material
    in the Operations menu. This opens the  
	Supplier Material for
    Purchase Order Line dialog box.
  
- Click New.
  
- In the  Component Part  field, specify the component
    part (the inventory part) that will be connected to the purchase. Either
    enter the code for the sales part or select it from the List of
    Values. If applicable, you can indicate a condition
    code in the Condition Code field.
  
- Enter the date on which the supplier needs the component
    parts.
  
- In the  Qty per Assembly  field, specify how many
    component parts are needed to manufacture or pack each purchase part.
  
- To issue the components using backflushing, select the Backflush
    check box, and specify a desired picking location as the backflushing location
    in the Backflush Location field.
  
- In the Supply Code  field, select from either
    Inventory Order or Project Inventory.
 (The Project Inventory supply code is allowed only for purchase order lines
    that are connected to project activities. In such cases, parts can be
    reserved and picked only from the project inventory of the connected
    project)
- Save when completed.
  
- Repeat steps 3—9 until all the component parts are
    entered. Then close the 
	Supplier Material for
    Purchase Order Line window.