Change General Supplier Agreement Terms
Explanation
When you renegotiate a supplier agreement, there might be changes in the general
conditions for the supplier agreement. This activity describes the different options that can be
changed in the header and in the General tab.
Prerequisites
  - A supplier agreement must have been entered.
- If you are changing the buyer, the new buyer must have been entered as a buyer in 
	Procurement Basic
    Data/Buyers.
- If you are changing the delivery terms and ship via code, the new terms must have been
    entered in  
	Delivery Terms and 
	Ship Via Codes. 
- If you are changing the payment terms, the new payment terms must have been entered in
    Payment Terms.
- If you are changing the supplier agreement group, the new supplier 
	agreement group must have been entered in Procurement Basic
    Data/Supplier Agreement Group.
System Effects
The general conditions are changed and will be used for applicable purchase order
lines, if the status of the supplier agreement allows purchasing.
If the supplier agreement has been changed from a local agreement into a group agreement,
it is possible to enter multiple sites in the Valid Sites tab.
Window
Supplier Agreement
Related Window Descriptions
Supplier Agreement
Supplier Agreement/General
Procedure
Open Supplier Agreement, then populate or query for the purchase agreement
or blanket purchase order you are renegotiating. All of the suggested changes below are
optional and are dependent upon the agreed terms you have with your supplier. 
  - To change the buyer, enter the new buyer in the Buyer field, either manually or by using
    the List of Values. The name of the buyer will automatically be changed.
- To change from local agreement to group agreement or vice versa, select
    (or clear) the Group Agreement check box in
    the header of the window. It is not possible to save it as a local agreement if there is
    more than one site entered in the Valid Sites tab.
- To change the parameters in the Selection Parameters group box, you can change the
    delivery terms, ship via code, and payment terms either manually or by using the List of
    Values. Note that the Ship Via Code that you are using on the
    supplier agreement has to be entered for all supplier addresses that you use in order to make the
    lead time calculations work.
- If the supplier agreement group should be changed, do so either manually or by using the List of
    Values in the Supplier Agreement Group field. The description will be filled in automatically. 
- In the Maximum Amount Option field, you can change the system effects regarding what
    happens when the amount specified in the supplier agreement is reached. For a description of
    the different options, look at the window description for the 
	General tab.
- If the review date should be changed, enter the new date in the Review Date field.
- The fields Supplier Agreement Reference and Termination Condition
	are free text fields and
    can be changed if applicable.
Save when completed.