Gantt
Usage
Use this window to view the graphical 
representation of one or several projects. It is also possible to do manual 
changes to the project activities and create a project network or perform a 
scheduling calculation.
The user can adjust the appearance of the Gantt chart and the information 
shown, by using the settings in the header of the window, or through various 
menu options. The Gantt window has these graphical features:
	- The project structure is shown beside the Gantt chart.
- Summary bars are shown for the project and sub project levels. These can 
	be expanded to show the underlying structure or collapsed using 
	corresponding menu options.
- Activities are 
represented by bars, where the beginning and end of the bar corresponds to the Early Start (ES) and Early Finish (EF) 
dates and the length of the bar corresponds to the Total Work Days of the 
activity. 
- Optionally, activity Calculated Cost Progress and Calculated Hours Progress 
	are represented by different bars on top of the activity bar.
- Milestone activities, i.e. activities that have work days 
  equal to zero, are represented as a diamond. 
- Optionally, time-critical objects connected to an activity can be 
	displayed. The objects 
that can be seen in the Gantt chart are Purchase Order line, Shop Order, Work Order 
and DOP Header.
- Optionally, activities with exceptions can be marked with a warning triangle.
- Optionally, activities that are on the critical path can be seen in red 
	color.
- Optionally, the working and non-working periods from the project calendar 
are shown in the Gantt.
The activity dates can be either set manually or through a scheduling 
calculation in the Gantt:
	- The activity Early Start, Early Finish and Total Work Days can be 
	manually adjusted by moving the bars or changing the length of the bars. 
- The activity network can be created in the Gantt, by adding dependencies between activities. The 
dependencies are represented by arrows between the activities and can be 
optionally shown or hidden as set in the 
Gantt header. Select the menu option Dependency Details to view or update 
the dependency information including the Predecessor activity, Successor 
activity, Dependency Type and Lag. 
- A scheduling calculation can be initiated by selecting menu option 
	Schedule Project.
Activity Diagrams
Establish Project Plan
Analyze Project Performance
Activities
Schedule Project Plan
Analyze Project Exceptions