Analyze Project Budget/Forecast
Explanation
This activity describes different 
features you can use to analyze a budget/forecast. Depending on what kind of analysis 
you want to do, there are different features:
	- Drill Down
- Periodical Cost Graph
- WBS Summary
- CBS Summary
- Budget vs Forecast
- Project Budget Analysis
By performing the Drill Down feature it 
is possible to gain knowledge about 
objects' underlying values and their 
connections. Periodical Cost Graph is a graphical overview showing accumulated 
values outlined over the activities' separate periods. This makes it possible to 
perform a quick comparison between different values. The WBS and CBS Summary are 
an overview for the whole project which shows both a summary for the level in 
the structure you have chosen and a summary for lower levels. There is also a 
detailed summary for the WBS and CBS elements on the lower levels. You can use both the WBS navigator and the 
CBS navigator to find the required level in the structures where you want to 
work. The Budget vs Forecast is a graphical overview of 
the budget compared to the selected forecast. It displays graphs for margin, 
profit and costs. It is also possible to break down the costs to lower levels. Use the Project Budget Analysis  
window 
to view the project key performance 
indicators.
Prerequisites
	- Drill Down feature requires that a snapshot has been created and has an Estimated value or higher (e.g. Planned).
- Periodical Cost Graph requires that the forecast values have been spread.
- CBS Summary requires that the project has a CBS Structure.
- Project Budget Analysis requires an active budget.
System Effects
None.
Window
Project Forecast
Project Forecasts
Project Forecast Version Line
Project Periodical Cost Graph
Project Budget Analysis
Project Snapshot Details
Related Window Descriptions
Project Forecast
Project Forecast/Cost
Project Forecast/WBS Summary
Project Forecast/CBS Summary
Project Forecasts
Project Forecast Version Line
Project Periodical Cost Graph
Project Budget Analysis
Project Snapshot Details
Procedure
Use the following procedure to perform a
Drill Down using the 
	Project Forecast window:
	- Open the 
	Project Forecast window and query for a project forecast version for which 
	you want to perform a Drill Down.
- Right-click on a line in the 
	Cost tab
	or Revenue tab, 
	point to Drill Down and then click either Snapshot Data or 
	Live Data, depending on which type of snapshot you have connected to that 
	forecast.
- Observe the detailed cost/revenue for each specific object.
- To view more details for a particular object, right-click on that object 
	and then click Object Details.
 
Use the following procedure to perform a
Drill Down using the 
	Project Forecast 
Version Line window:
	- Open the 
	Project Forecast 
	Version Line window and query for a project forecast version for 
	which you want to perform a Drill Down.
- Right-click on the window, point to Drill Down and then click 
	either Snapshot Data or Live Data, depending on which type of 
	snapshot you have connected to that forecast.
- Observe the detailed cost/revenue for each specific object.
- To view more details for a particular object, right-click on that object 
	and then click Object Details.
 
Use the following procedure to view a 
Periodical Cost Graph on an existing forecast version:
	- Open the 
	Project Forecast or 
	Project Forecasts window and query for a project forecast version for which you want to 
	view a Periodical Cost Graph.
- Right-click on the window, and then click Periodical Cost Graph.
- Observe the graph and the cost/revenue spread across periods.
- Click on the 
	Data tab 
	to get more information about the data in the graph.
 
Use the following procedure to view a 
WBS Summary using the 
	Project Forecast window:
	- Open the 
	Project Forecast window and query for a project forecast version for which 
	you want to view a WBS Summary.
- Click on the 
	WBS Summary 
	tab.
- Select Cost or Revenue from the
	Display what list box according to the requirement.
- Choose desired level in the WBS navigator.
- This level shows the cost/revenue directly reported on the selected WBS node.
- Lower levels shows the accumulated cost/revenue of all sublevels underneath the 
	selected WBS node. 
- Detailed information about the lower levels is specified in a separate 
	table.
 
Use the following procedure to view a 
CBS Summary using the 
	Project Forecast window:
	- Open the 
	Project Forecast window and query for a project forecast version for which 
	you want to view a CBS Summary.
- Click on the 
	CBS Summary 
	tab.
- Select Cost or Revenue from the
	Display what list box according to the requirement.
- Choose desired level in the CBS navigator.
- This level shows the cost/revenue directly reported on the selected CBS node.
- Lower levels shows the accumulated cost/revenue of all sublevels underneath the 
	selected CBS node.
- Detailed information about the lower levels is specified in a separate 
	table.
 
Use the following procedure to view the Budget vs 
Forecast using the 
	Project Forecast window:
	- Open the 
	Project Forecast window and query for a project forecast version for which 
	you want to analyze the budget against the forecast.
- Click on the 
	Budget vs Forecast 
	tab.
- Observe the graphs for margin, profit and cost 
	breakdown. In the Profit and Breakdown of Costs graphs the bars to the left 
	displays information from the budget and the bars to the right displays 
	information from the selected forecast.
- Select which level of the breakdown of costs you 
	want to display. You can choose between Top, CBS level 1 and Cost Element 
	level.
 Note: CBS Level 1 is only displayed if the project has a CBS structure.
- Optionally, click on a bar in the Breakdown of Costs graph to drill down 
	to the relevant forecast lines.
 Note: This can only be done when you have chosen the Top or Cost Element 
	level.
- Optionally, select the Display Data check 
	box to get more information about the data in the Breakdown of Costs graph.
 
Use the following procedure to view the
Project Budget Analysis:
	- Open the 
	Project Budget Analysis window and query for a project forecast 
	version that you want to view.
- The header shows the projects' selected 
	Forecast Version ID and the Budget Version ID of the active 
	budget.
- If a forecast line has the same Sub Project, 
	Activity ID and Cost Element as the active budget, that line 
	shows both the forecast values and the budget values from the active budget.
	
- Observe the key performance indicators for the 
	selected forecast version.