Approve Budget/Forecast
Explanation
This activity may be done by the budget/forecast owner who approves the 
budget/forecast 
directly, or by using a pre-defined approval routing where individuals can 
approve the budget/forecast in parallel or in sequence.
A budget/forecast may be approved either from status Reviewed if no approval routing 
exists or from status Approval in Progress if approval steps have been defined 
on the approval routing linked with the budget/forecast.
Prerequisites
	- Budget/forecast lines if defined must be confirmed prior to approval.
- The budget/forecast version must have the status Reviewed or Approval in 
	Progress. 
- If approval steps have been defined for the budget/forecast version they must be 
completed.
- If approval steps have been defined, the approval process cannot contain 
	any steps with the status Rejected.
System Effects
The Status Approved is assigned to the budget/forecast version. 
Window
Project Forecasts
Project Forecast Info
Related Window Descriptions
Project Forecasts
Project Forecast Info
Procedure
Use the following procedure to approve a budget/forecast version:
	- Open the Project window and 
	right click and select the Project Forecasts menu option, which will 
	open the the 
	Project Forecasts 
	window with the related forecasts for the project. You can also open up the 
	Project Forecasts or 
	Project Forecast Info window to perform 
	this activity. 
- Query for the budget/forecast version that you want to set 
	to Approved. 
- Right click, click Status and then click Approve.