Cancel Project Supply Request
Explanation
Use this function to remove the Purchase Requisition or cancel 
the Purchase Order, DOP 
Header or Shop Order that
has been previously created for a miscellaneous demand.
Prerequisites
  - A Purchase Requisition must have been created for a miscellaneous 
  part, no part or rental part.
- If a Purchase Order had been created from the Purchase Requisition, the Purchase Order
    must be in status either  Planned,  Released or  Confirmed. The purchase order line 
  must be cancelled manually from the Purchase Order first.
- A DOP Header in status  Created must have been created 
  for a miscellaneous part. 
  
- A shop order in status either  Planned,  Released or 
   
  Reserved must have been created for a miscellaneous part.   
System Effects
  - The record for Requested Quantity and Requested Date
  will be cleared.
- If only a Purchase Requisition exists, the
    Purchase Requisition line is deleted.
- When the Purchase Order line is cancelled, the connected 
  Purchase Requisition line is re-opened and set to status  Released.
- The DOP header is cancelled.
- The shop order is removed.
Window
Project 
Navigator/Demand/Misc.
Parts
Activity/Demand/Misc. Parts
Project/Demand/Misc.
Parts
Project
Navigator/Demand/Misc. No Parts 
Activity/Demand/Misc. No Parts 
Project/Demand/Misc. No Parts 
Project 
Navigator/Demand/Misc. 
Rental Parts
Activity/Demand/Misc. 
Rental Parts
Project/Demand/Misc. 
Rental Parts
Related Window Descriptions
Project
Navigator/Demand/Misc. Parts
Project
Navigator/Demand/Misc. No Parts 
Project Navigator/Demand/Misc. 
Rental Parts
Procedure
1. Select the miscellaneous demand lines to be
canceled.
2. Use the right mouse button option Cancel Project Supply Request to remove the
pegged supply request.