Connect/Disconnect Contract Change Orders
Explanation
Use this activity to connect contract change order forecasts to a 
budget/forecast version.
Prerequisites
	-  A contract change order with a contract change order forecast 
	should exist for the project.
System Effects
	- An existing contract change order forecast is connected to the selected 
	budget/forecast version and the ETC Contract Change 
	Order column will be added to the list of project forecast lines.
- If it is a disconnection: The existing contract change order forecast is 
	disconnected from the selected budget/forecast version. When all the connections 
	are disconnected from the selected budget/forecast the ETC Contract Change 
	Order column will be removed from the list of project forecast lines.
- When using update, all the values in the ETC Contract Change Order 
	column in the project forecast lines will be recalculated for the contract 
	change order forecast.   
Window
Project Forecast
Related Window Descriptions
Project Forecast
Forecast Connection 
Contract Change Order
Procedure
Use the following procedure to connect a contract change order forecast to the selected 
budget/forecast 
version:
	- Open the 
	
	Project Forecast window, query for the project 
	budget/forecast version for which you want to connect a contract change 
	order forecast. 
- Right click on the window, click Forecast Connection. The dialog box opens up.
- Select the 
	
	Contract Change Orders tab. 
- Click New to enter a new line.
- In the Change Order No field, use the List 
	button to select a previously created contract change order forecast that 
	you want to connect to the selected budget/forecast version. 
- Click OK.
Note. Alternatively, it is also possible to use Select 
	Batch to select more than one contract change order forecast.
Use the following procedure to disconnect a contract change order forecast 
from a selected budget/forecast version:
	- Open the 
	
	Project Forecast window, query for the project 
	budget/forecast version from which you want to disconnect the contract change 
	order 
	forecast.  
- Right click on the window, click the Forecast Connection menu 
	option. The Forecast Connection dialog box 
	will open.
- Select the Contract Change Orders tab.
- Select the required row and click Remove.
- Click OK. 
Use the following procedure to update a contract change order forecast in a selected 
budget/forecast 
version:
	- Open the 
	
	Project Forecast window, query for the project 
	budget/forecast version for which you want to update the contract change 
	order 
	forecast.  
- Right click on the window, and click Forecast Connection. The dialog box opens up.
- Select the 
	
	Contract Change Orders tab. 
- Select a row and click Update.
- Click OK.