Connect Existing Snapshot
Explanation
This activity enables the connection of an already created snapshot to the selected 
budget/forecast version. Any snapshot created with the same cut-off date and time can 
be connected to the budget/forecast.
Prerequisites
	- More than one snapshot should exist for the budget/forecast with the same cut 
	off date and time. 
- If a snapshot has been connected to the budget/forecast version it must be disconnected first 
	to enable a new snapshot connection. 
System Effects
	- An existing snapshot is connected to the selected budget/forecast version.
- If a snapshot is connected to the budget/forecast version this snapshot will be 
	disconnected and replaced by the snapshot selected for connection this time. 
	All Actual, Committed and Used cost on the 
	Cost tab of the budget/forecast 
	will be disconnected as well.
- The 
	estimated, planned, preliminary, posted, and actual revenue on the 
	Revenue tab of the selected 
	budget/forecast version 
	will be updated with reference to the new snapshot.   
Window
Project Forecast Info
Project Forecasts
Related Window Descriptions
Project Forecasts
Project Forecast Info
Project
Connect Snapshot
Procedure
Use the following procedure to disconnect a snapshot from a selected 
budget/forecast 
version:
	- Open either the 
	Project Forecasts or 
	
	Project Forecast Info window query for the project 
	budget/forecast version for which you want to disconnect the snapshot. You 
	can also open the Project window and 
	right click and select the Project Forecasts menu option, which will 
	open the the 
	Project Forecasts 
	window where you can query for the budget/forecast version. 
- Right click on the window, click Snapshot and then click 
	Disconnect. The message, "Do you really want to disconnect the current 
	snapshot from the forecast version?" is displayed. 
- Click OK to confirm the need for the disconnection.
Use the following procedure to connect a snapshot to the selected 
budget/forecast 
version:
	- Open either the 
	Project Forecasts or 
	
	Project Forecast Info window query for the project 
	budget/forecast version for which you want to connect a snapshot. You can 
	also open the Project window and 
	right click and select the Project Forecasts menu option, which will 
	open the the 
	Project Forecasts 
	window where you can query for the budget/forecast version.
- Right click on the window, click Snapshot and then click 
	Connect. The 
	Connect Snapshot dialog box opens up. 
- In the Number, Acc. Period or Date field, use the List 
	button to select one of an existing set of snapshots previously created and 
	connected on the selected budget/forecast version. 
- Click OK.