Connect/Disconnect Resource Forecast
Explanation
Use this activity to connect a resource forecast to a budget/forecast 
version.
Prerequisites
	- A resource forecast should exist for the project.
- The project doesn't have an active budget using net change budget 
	control
System Effects
	- An existing resource forecast is connected to the selected 
	budget/forecast version and the ETC Connected column 
	will be added to the list of project forecast lines.
- If it is a disconnection: The existing resource forecast is disconnected 
	from 
	the selected budget/forecast version. When all connections are disconnected 
	for the selected budget/forecast the ETC Connected column will be removed 
	from the list of project forecast lines.
- When using update, all the values in the ETC Connected column in the project 
	forecast lines will be recalculated for the resource forecast. If posting control 
	changes have been done even the cost elements may be changed. 
Window
Project Forecast
Related Window Descriptions
Project Forecast
Forecast Connection 
Procedure
Use the following procedure to disconnect a resource forecast from a selected 
budget/forecast 
version:
	- Open the 
	
	Project Forecast window, query for the project 
	budget/forecast version for which you want to disconnect the resource 
	forecast.  
- Right click on the window, click the Forecast Connection menu 
	option. The Forecast Connection dialog box 
	will open.
- Select the Resource Forecast tab
- Select the required row and click Remove.
- Click OK. 
Use the following procedure to connect a resource forecast to the selected 
budget/forecast 
version:
	- Open the 
	
	Project Forecast window, query for the project 
	budget/forecast version for which you want to connect a resource forecast. 
- Right click on the window, click Forecast Connection. The dialog box opens up.
- Select the Resource Forecast tab. 
- Press New to enter a new line.
- In the Resource Forecast Version ID field, use the List 
	button to select an existing set of previously created resource forecasts 
	that you want to connect to the selected budget/forecast version. 
	Alternatively, it is also possible to use Select 
	Batch to select more than one resource forecast.
 Note. It is not possible to connect a resource forecast if the project has 
	an active budget using net change budget control
- Click OK.
Use the following procedure to update a resource forecast from a selected 
budget/forecast 
version:
	- Open the 
	
	Project Forecast Info window, query for the project 
	budget/forecast version for which you want to update the resource 
	forecast.  
- Right click on the window, and click Forecast 
	Connection. The dialog box opens up. 
- Select a row and click Update.
- Click OK.