Copy Structure
Explanation
This activity is about copying a cost breakdown structure.
Prerequisites
	- A Cost breakdown structure must already exist to copy from.
System Effects
	- The Copied From field in the structure header will be filled with 
	the original cost breakdown structure ID.
- Once the structure is copied it can then be connected to a project and be 
used in budgeting and forecasting for the project.
Window
Project Cost 
Breakdown Structure
Related Window Descriptions
Project Cost Breakdown Structure 
Copy Structure
Procedure
	- Open the Project Cost Breakdown Structure window and 
	populate the required structure.
- Right-click and select the Copy Structure option.
- Enter the new structure ID and description.
- Click OK to create and copy the values into the new structure.