Create Integration Configuration for Basic Data
Explanation
This activity is used to create an integration configuration record for the 
basic data integration between IFS Applications and the  Primavera 
Project Management module (Primavera).
Basic data in IFS/Project are calendars and resources. In order to be able to export or 
import projects with basic data to/from Primavera it is necessary to have the 
basic data already existing on the receiving side. This can be done by exporting 
or importing the basic data separately, or by entering the basic data manually. 
Note that while resources can both be exported and imported, calendars can only 
be exported. The integration of data between IFS/Project and Primavera is described in 
detail in About Integration to Primavera Project Management.
Integration configurations for basic data are created and saved as records in 
the Integration Configuration/Basic Data Integration 
tab, and can therefore be reused any number of times. A record can be 
selected to perform a basic data analysis, or to initiate a basic data export or 
import.
Prerequisites
	- The Primavera Project Management module should be installed.
- An integration setup record should exist in the 
	Integration Setup/Integration Database Setup tab.
- If it is required to export calendars, they should be defined in the 
	Integration Setup/Integration Calendar Setup tab.
- If resources are to be included in the import, a default calendar and a 
	default cost element must be defined for that resource in the 
	Integration 
	Setup/Integration Resource Setup tab.
System Effects
	- The integration configuration record is created, ready to be used 
	for exports or imports of basic data.
Window
Integration 
Configuration 
Related Window Descriptions
Integration Configuration/Basic Data 
Integration
Procedure
	- Open the Integration Configuration 
	window and click on the Basic Data Integration tab.
- Create a new 
integration configuration record.
- Enter a value in the Integration ID field.
- Select Export or Import in the Direction field.
	- Optionally you can do one or more of the following:
	- Enter a calendar in the Calendar field if you want to export a single calendar.
- Enter the resource company that has the resources that are to be 
	exported/imported in the Resource Company field if you want to 
	export/import resources. 
- Enter a Resource 
	Company and select the Resource Calendar checkbox if you wish to 
	export resources and their related resource 
	calendars.
	- Select a valid value in the Setup ID field which is the identity of the 
setup used to access Primavera.
- Select a value in the Owner ID field.
- Optionally, enter a note.
- Save the record.