Create Integration Configuration for Project Data
Explanation
This activity is used to create an integration configuration record for the 
project data integration between IFS Applications and Primavera Project 
Management (Primavera). Currently, the project data includes the project 
calendar, the WBS structure, resource assignments, dependencies and constraints.
The integration of data between IFS/Project and Primavera is described in detail in the 
About Integration to Primavera Project Management.
Once integration configurations for project data are created and saved they can 
be reused a number of times to perform a project data analysis, or to initiate a 
project data export or import.
Prerequisites
	- The Primavera Project Management module should be installed.
- A project should exist in IFS/Project.
- An integration setup record should exist in the 
	Integration Setup/Integration Database Setup tab.
System Effects
	- The integration configuration record is created and ready to be used for 
	exports or imports of project data.
Window
Integration 
Configuration 
Related Window Descriptions
Integration Configuration/Projects 
Integration
Procedure
	- Open the Integration Configuration/Projects 
	Integration tab and create a new integration configuration record.
- Enter a value in the Integration ID field.
- Select a project from IFS/Project to export, or import, in the 
	Project ID field and select the direction in the Direction field.
- Enter the identity of the project in Primavera that will receive the 
	exported data, or the one that is to be imported, in the External Project 
	ID field.
- Select the Project Calendar checkbox if the project calendar in 
	IFS/Project should be the same in Primavera project. Note that the calendar 
	must exist as basic data in Primavera, and calendars cannot be imported to 
	IFS/Project.
- Select the Dependencies and Constraints checkboxes if you 
	want them to be included in the export or import.
- Select the Resource Assignments checkbox if the resources of the 
	project are to be assigned to the receiving project during the 
	export/import. Note that resources must exist as basic data in IFS/Project 
	and Primavera.
- Enter a valid value in the Setup ID field.
- Enter a value in the Owner ID field.
- Optionally, enter a note.
- Save the record.