Create Project Spread Profile
Explanation
Perform this activity to create spread profiles which can be 
used to distribute hours or amounts into different date ranges or periods in 
project resource forecasting and project budgets and forecasts. The purpose of 
these spread profiles is to simplify the spreading so that you can select and 
use a predefined spread profile to perform the spreading instead of entering 
spreading manually per date range or period.
A spread profile can also be set as the default profile for a resource forecast, 
cost forecast and/or revenue forecast. When e.g. a resource forecast line is 
added in a company the spread profile that is set as default will be proposed 
automatically for it.
Prerequisites
System Effects
  - A spread profile is created which will be made available for connection to
  resource forecast or project budget and forecast lines.
Window
Project Spread Profile
Related Window Descriptions
Project Spread 
Profile
Procedure
  - Open the Project Spread Profile 
	window.
- Create a new record in the 
	header (F5).
- In the Spread Profile ID field enter an ID for the spread 
	profile.
- In the Description field enter a 
	description of the spread profile. 
- In the Company field enter the company for 
	which this spread profile is valid. Spread Profile ID together with
	Company should be unique. If you do not enter a value in the Company 
	field this 
	spread profile will be valid for all companies.
- In the No of Intervals field enter the number of 
	intervals that should be used in this spread profile. If e.g. 4 intervals 
	are entered, 4 interval rows with a 
	proposal of 25 % distribution in each interval will be created automatically when you save the header.
 Note. If the number of intervals are increased or decreased later, the 
	percentage of distribution needs to be updated manually on the rows.
- Optionally, if values are entered for Gradient 
	and Mid-Point (these fields are hidden by default and need to be 
	enabled if they should be used) the distribution will be done according to 
	an S-Curve. In the Gradient field, enter the value to determine the 
	steepness of the S-Curve. In the Mid-Point field, enter the point at 
	which half of the cost/revenue should have been distributed. If no values 
	are entered in the Gradient and Mid-Point the distribution 
	will be done evenly between the intervals.
- Click Save to save the header.
- Optionally, change the % Distribution on the 
	intervals so that it suits the spread profile that should be entered.
- Optionally, if the spread profile should be a 
	default spread profile for the resource allocation, cost 
	spread and/or 
	revenue spread select the corresponding check boxes.
 Note. Only one spread profile can be default profile for 
	e.g. resource allocation in the same company. If you select another spread 
	profile as default profile for the resource allocation in that company, the check 
	box will be automatically cleared for the previous spread profile.
- Click Save and save the changes in the 
	interval rows.