Define Budget Control Rules
Explanation
Budget control rules define how the project transactions are validated 
against the budget and will work only from the budget consumption point onwards. The project specific budget control rules have to be defined for 
a cost element or a cost breakdown structure (if used) and can be defined together for selected 
code parts.
If a budget is defined on a very detailed level it might become cumbersome to 
define all rules manually. It is then possible to define budget rules by 
fetching details from a given budget version to create a new set of control 
rules using the Define Budget Control Rules 
Assistant. If the user 
plans to adopt this approach in creating rules, it is assumed that a fully 
defined budget is available to fetch information.
Control total for each budget line will be calculated based on the actual 
budget of the selected budget. If there are no budget lines defined for the 
rules that are defined here, control total against those rules will be equal to 
zero. The Control Total for each control rule can be viewed on the 
Project Budget Control Summary window. 
Control as budgeted is used to control project costs strictly at the same level of 
its active 
budget, thereby eliminating the need for the definition of explicit budget 
control rules. 
Control on total budget is used to allow you to decide whether the project 
should be controlled against the total budget or not. If this check box is 
selected, total cost consumed in the project in all project cost elements will 
be considered with the total budget when controlling further consumptions. If 
not, only the cost consumed against the budget controlled project cost 
elements will be considered with the budget based on the budget control rules.
Prerequisites
	- An active budget should exist.
- Only the code parts selected on the 
	
	PCE Code Part tab can be used against each cost element in 
	creating budget rules.
- If the control as budgeted function is to be used the 
Budget Control On checkbox must be selected in order to select the Control As 
Budgeted check box. 
- A consumption point must be defined for the company in
Project Basic/Budget Control tab 
	for the rules to be enforced.
System Effects
	- Project budget control rules will be enforced 
for all active project budgets having Budget Control enabled.
- If the Control As Budgeted check box is 
	selected on a project it will not be possible to change control rules 
	manually on that project. 
Window
Project Budget Control Rules List
Project Budget 
Control Rules 
Define Budget Control Rules Assistant - Step 1
Projects
Project
Related Window Descriptions
Project Budget Control Rules List 
Project Budget Control Rules
Define Budget Control Rules 
Assistant - Step 1
Projects
Project/General
Procedure
Use the following procedure to define budget control rules manually:
	- Open the Project Budget Control Rules List window.
- Click New to create a new 
	record.
- In the Project ID, Sub Project ID and Activity ID 
	field, use the List of Values to select a project, sub project or an 
	activity for which you want to define budget control rules. Alternatively 
	you can leave the fields for sub project ID and activity ID blank to create 
	a general rule for the project.
- In the Cost Element field, use the List of Values to select a 
	cost element or node on which you want to enforce budget control rules. 
- Use the List of Values in the desired Code Part fields to select code 
	parts for which you want to enforce budget control rules. 
- Use the List of Values in the Currency Code field to select the 
	currency for which you want to enforce budget control rules.
- Click Save.
Use the following procedure to define budget control rules using the 
Define Project Budget Control Rules Assistant: 
	- Open the Define Project Budget Control Rules 
	Assistant.
- In the Company field, use the List button to select the 
	company for which you want to define control rules.
- In the Project field, use the List button to select the project for which you want to define control rules. The 
	Project Budget Version field then automatically inherits the forecast 
	version that has been set as the Active Budget. 
- In the Existing Rules group of fields, you can choose one of the 
	following options based on your requirement:
 Override Existing Rules: Select this option to generate rules which 
	will replace any existing budget control rules defined on the selected 
	project
 Append Existing Rules: Select this option to generate rules which 
	will be added to any existing budget control rules defined on the selected 
	project.
- Click Next. 
- Select all unique levels in the WBS (Project/Sub Project/Activity) on 
	which you want to enforce the control rules. If you want to select the whole 
	project or e.g. all activities under a Sub Project, right click on the 
	desired level and RMB Select All.
- Click Next.
- Select all levels in the CBS or the cost elements on which you want to 
	enforce the control rules. If you want to select the whole structure or e.g. 
	all levels under a CBS Node, right click on the desired level and click 
	Select All.
- Click Next.
- Select the currency codes on which you want to enforce the control 
	rules. If you want to select all currencies, right click Select All 
	in the Select Currency Code column.
- Click Finish.
- You can modify the created control rules if required.
- Click Save.
Use the following procedure to control a project as 
budgeted:
	- Open either the 
	Projects or 
	
	Project 
	window and query for the required project. 
- Right click and then 
	click Enable/Disable Budget Control 
	to enable budget control. 
- Right click and then 
	click Control As Budgeted.
	
To enforce the control on the total budget:
	- Right click and select Control on Total Budget.