Define Cost Element Code Part Demands on Project
Explanation
This activity is used to define a set of project-specific code parts that are to be used in 
budgeting against each cost element. By selecting a code part against a cost 
element, it makes that code part mandatory in forecast lines, for that cost 
element.
Prerequisites
	- Cost elements should be defined on the user's company in the 
	Project Cost/Revenue Elements window.
- Cost elements code part demands must be predefined on a company template 
	in Project Basic/Cost Element Code Part Demand tab. 
System Effects
	- Changes done on this tab will affect only the project on which the 
	settings have been defined. 
Window
Project
Related Window Descriptions
Project
Project/PCE Code Part
Procedure
Use the following procedure to define project-specific code part demands on a cost element:
	- Open the 
	Project window, and Query for 
	project on which the cost element code part demands have to be defined. 
- Click
	on the PCE Code Part tab.
- Click on a row in the table and click New (F5) to create a new 
	record.
- In the Cost Element field, use the List of Values to select a 
	cost element that is has been for the particular company. 
- Select the check boxes of the desired code parts. 
	
- Click Save.