This activity is used to import basic data from IFS Applications to Primavera 
Project Management (Primavera). Basic data in IFS/Project are calendars and 
resources. Calendars can only be exported from IFS/Project while resources can 
be both imported and exported. An import of basic data will create new records 
in IFS/Project, or update the information in existing basic data. The 
basic data must exist in IFS/Project before it can be assigned to a project through a project 
integration.
Integration configurations are created and saved as records in the
Integration Configuration/Basic Data Integration 
tab. They can be reused any number of times to perform a basic data analysis, or to initiate a basic data 
integration. 
Before the actual import is started it is possible to run a data analysis that 
will check the most fundamental differences in business logic between 
IFS/Project and Primavera. Executing the data analysis functionality is a 
recommended part of the process of integrating data; and it will give 
information about data that may need to be rectified before performing the 
integration, in order for the integration to be successful. The analysis can be 
started separately using the Analyze Data menu option, or in combination 
with the integration by using the Analyze Data and Run Integration menu 
option. While the analysis is optional, but recommended, the integration can also 
be run without it by using the Run Integration menu option.
When initiating a basic data import, the basic data from both IFS/Project and 
Primavera is compared in order to find the changes that will occur to the basic 
data, should the import be completed. This information is displayed in the
Compare Data dialog box that will open. Thus it is possible to analyze the 
consequences of updating the basic data before the actual import. Once the basic 
data from IFS/Project and Primavera has been compared, the actual import can be 
performed. A completed basic data import, or basic data analysis, results in a 
history record. 
The details for the basic data import are given in About Integration to Primavera Project Management.
Integration Configuration/Basic Data 
Integration
Integration Messages
Compare Data
Integration History
Note: If the basic data analysis results in integration messages of type Error, basic data must be rectified before running the integration. Correct the data accordingly in IFS/Project or Primavera. Continue to the activity Analyze Integration Messages to get more detailed help on how to rectify problems. It is optional to take action on the other types of integration messages, i.e. warnings or information messages.
Notes: