Import Project Plan from IFS/Project to Microsoft Project
Explanation
A project in IFS/Project can be integrated with a Microsoft Project file by 
using the IFS Microsoft Project Add-in. When this Add-in is 
installed, you will be able to access IFS/Project by using the IFS 
Applications menu shown on the menu bar in Microsoft Project. In this menu, 
select the Connect to IFS option in order to establish a connection to 
the desired IFS database.
When connected to an IFS database, you can import a 
project plan from IFS/Project to the active Microsoft Project file through the 
import function in the IFS Applications menu. All information necessary 
for project planning purposes is handled in the integration, such as project 
information, the sub project structure and activities with their relevant 
information. In addition, for each import, it can be configured whether certain data 
types should be transferred, such as dependencies, constraints, resources and 
resource assignments.
An import can either update an existing project or create an entirely new 
project plan in an empty Microsoft Project file. The import will update the 
entire Work Breakdown Structure (WBS) by adding new activities and sub projects, 
as well as modifying existing activities and sub projects. As a result of the 
import, activities and sub projects that exist only in the Microsoft Project file 
will be deleted. 
Prerequisites
  - Microsoft Project must be installed.
- 
  	The IFS MSP Add-in must
    be installed. Refer to the
    Release Notes for more details.
- The Project ID must exist in 
	IFS/Project.
- You must have access to the 
	entire project to perform the import.
System Effects
  - When the Import From IFS 
	menu option is run for the very first time, a new table is automatically 
	created in Microsoft Project which is used for the integration to 
	IFS/Project.
- The active Microsoft Project 
	file is updated. If there is no active file in Microsoft Project, a blank 
	project is opened and updated.
- The Microsoft Project file 
	is updated with information from the IFS project. Data in the IFS/Project will be 
	imported to the MS Project as specified in detail in
	About Integration to 
	Microsoft Project.
 
  - The sub projects and activities will be imported as tasks to Microsoft 
	Project. All tasks will be outlined in a hierarchical order according to 
	their placement in the subproject structure in IFS/Project. Activities are 
	outlined below their respective sub projects.
- Activities and sub projects that exist only in the Microsoft Project file 
	will be deleted.
- If the Resource Assignments check box in the Import Project 
	from IFS 
	dialog box is selected, all resource allocations to project activities are 
	imported together with the basic data for these resources. By selecting the
	Resources check box, all resources connected to the company of 
	project including those that are not allocated, will be imported with the 
	basic data information. Resource information in Microsoft Project will be 
	created or updated.
- If the Constraints 
	check box in the Import Project from IFS dialog box is 
	selected, information about constraints on activities will be imported. If 
	no constraint type is set on the activity in IFS/Project, the activity in 
	Microsoft Project will get the As Soon as Possible default constraint type. 
	Constraints in Microsoft Project will be created or updated.
- If the Dependencies 
	check box in the Import Project from IFS dialog box is 
	selected, information about activity dependencies including dependency type 
	and lag in days, will be imported. Dependencies in Microsoft Project will be 
	created, updated or deleted.
 
Window
N/A
Related Window Descriptions
Import Project from IFS
Procedure
	- Open Microsoft Project and click on the IFS Applications 
	menu option on the menu bar.
- Select the Import From IFS option and the
	Import Project from IFS dialog box will open.
- Click on the Resources, Resource 
	Assignments, Dependencies or Constraints check boxes 
	according to your requirement.
- Enter the IFS Project ID or select it from the List of 
	Values.
- Click Start.
- Once the import is completed click OK to close the dialog box.