Insert Project ID
Explanation
Create the project in the system by registering the project ID, project name, project description, manager,
company and calendar.
A wizard is available to ease the process of entering the data. The wizard lets
you specify the project details and project milestones, project sites and
project access. 
Prerequisites
  - A company must exist.
- A calendar must exist. It must be predefined in
    
	Calendar.
- The person to be registered as project manager must have a user ID in 
	
	Person.
- If you want to connect a customer, the must be predefined
    in 
	Customer.
System Effects
  - A project is created, and you can start creating a
    project structure with subprojects, activities, and tasks.
- The project is in Initialized status.
- If project
    access was disabled, and all users in the system will have access to all
    parts of the system.
- If project access was enabled, the project manager will always have
    access to all parts of the project. The sub project manager will always have
    access to their own sub project and the sub project structure beneath. 
 The system has automatically created records in Project/Project Access/Access Definition  to grant access to all
    teams that have the Access to New Projects checkbox marked in 
	Project
    Team. The access for these and other teams can be modified in 
	Project/Project Access/Access Definition.
Window
Project Navigator
Projects
Project
Related Window Descriptions
Projects
Project
Define Project Information 
(Step 1 in the Create New Project Assistant)
Procedure
Create a new project by using the Create New Project 
Assistant:
  - Open Project Navigator,
	Projects or 
	Project.
- Click the right mouse button menu option Create New Project, and fill in all 
	the required information.
- Click Finish.
Or you can do it manually in Projects or 
Project. 
  - Create a new record. 
- Enter the project ID, project name, project description, manager, company
    and calendar (the default company
    automatically appears). The manager must be a person connected to a system
    user. The rest of the information (such as program ID,
    currency type, customer,
    customer responsible, customer project ID, planned start date, planned finish
    date, planned revenue, planned cost and probability to win)
    can be registered either now or later. 
- Verify/change the setting of Project Access On.
- Select the Project Unique Procurement check 
	box if you want the purchase orders and purchase invoices to be created 
	uniquely for this project and not combined with other projects. Similarly, 
	select the Project Unique Billing check box if u want sales invoices 
	to be created uniquely for this project.
- Save.
- If project access was enabled, you might want to define/modify the team
    access. See the activity Define Project Access
    for more information.
- You can now use the tabs in 
	Project to enter more
    information if desired.