Refresh ETC Currency Values
Explanation
When using multicurrency budgeting and forecasting you have a choice of using 
the same currency rates throughout the period of the forecast or change it if 
the necessity arises. Once you have changed the currency rates you are able to 
refresh the existing budgeted/forecasted values of the selected forecast.
Prerequisites
	- Multicurrency budgeting and forecasting and/or project currency should be in 
use.
System Effects
	- The values for the base currency B&F rate and 
	project currency types in the forecast will be recalculated with 
the new rates.
Window
Project Forecast  
Related Window Descriptions
Update ETC Currency 
Amounts
Procedure
	- Open the Project Forecast window and 
	query for the required forecast version.
- Right-click on the header and click the Update Currency Amounts 
	menu option.
- In the Update ETC Currency Values dialog 
	box that appears click the Project Currency check box and/or the Base 
	Currency at B&F Rate check box depending on the currency you 
	require.
- Click OK.