Spread Forecast Amount
Explanation
Cost/revenue spreading is usually done on a budget/forecast line if the ETC cost/revenue needs to be distributed into 
specific time periods when they are most likely to occur. It will be possible to spread cost/revenue into accounting periods manually as well as 
to get assistance with distributing the budgeted/forecasted amount using pre-defined 
spreading profiles. It is only possible to spread the part of 
the ETC that is not connected to a resource forecast or a 
contract change order.
Prerequisites
	- A project budget/forecast line with an ETC amount 
	that has not only been generated from resource forecast connections, should 
	exist.
- The Cut-Off Date specified on the project budget/forecast version 
	should reside on an accounting period that exists for the company of the 
	project.
System Effects
	- The adjusted part of the ETC amount is spread over the accounting periods between (and 
including) Start Date and End Date.
- The Spread Profile check box is selected to indicate that the cost/revenue has 
been spread into accounting periods.
- The ETC Spread Date Exception check box is checked if there exists 
amounts spread outside the Start Date and End Date.
- If the Start Date and End Date are not specified, the 
	system will fetch them from the Project Work Breakdown Structure based on 
	start and end dates of the Project, Sub Project and Activity of the budget/forecast 
	line.
Window
Project Forecasts
Project Forecast Version Line
Project 
Forecast Info
Related Window Descriptions
Project Forecasts
Project Forecast 
Version Line
Project Forecast Info/Cost
Project Forecast Info/Revenue
Spread Forecast Amount
Procedure
Use the following procedure to spread the cost/revenue on a budget/forecast line:
	- Open the 
	Project Forecast Info window and click on the 
	Cost tab or 
	Revenue tab depending on the requirement. You can also open up the 
	Project Forecast Version Line window to perform 
	this activity. 
- Query for an existing budget/forecast line for which you want to spread cost/revenue.
- In the Start Date field, enter a date on which you want to start 
	the cost/revenue spreading for the particular budget/forecast line. 
- In the End Date field, enter a date on which you want to end the 
	cost/revenue spreading for the particular budget/forecast line.
	
- In the Spread Type field, use the drop down list to select the 
	type of budget/forecast spreading required for the particular budget/forecast line 
	depending on the requirement:
		- Manual: Enables manual entry and distribution of costs/revenue for 
		each of the spread periods.
- Profile: Produces a linear or nonlinear distribution of cost/revenue among 
		the periods using a predefined spread profile.
 
- Click Save.
- Right click on the window and then click Spread 
	with Profile.
- In the Spread with Profile dialog box, select one of the 
	following options: 
	
		- Use Spread Profile from Line: Spreads cost/revenue as defined on the 
		budget/forecast line. 
- Override Spread Profile on Line: Enables the selection and entry 
		of spread profiles different from those defined on 
		the budget/forecast line.
 
- Click OK.
Use the following procedure to spread cost/revenue using the 
Project Forecasts window.
	- Open the Project Forecasts window, right click 
	and then click Spread with Profile.
- Click OK to confirm the message that is displayed. 
- In the Spread with Profile dialog box, select 
	what is to be spread .i.e. cost and/or revenue and then one of the 
	following options: 
	
		- Use Spread Profile from Line: Spreads cost/revenue as defined on the 
		budget/forecast line. 
- Override Spread Profile on Line: 
		Enables the selection and entry 
		of spread profiles different from those defined on 
		the budget/forecast line.
 
- Click OK.
Use the following procedure to view or modify complete details on the cost/revenue 
spread:
	- Select single or multiple budget/forecast lines from the 
	Cost 
	tab Revenue tab on the 
	Project Forecast Info window and right click and 
	then click Forecast Spread Details. You can also do similar in the 
	Project Forecasts window where single or multiple 
	budget/forecast versions can be chosen and budget/forecast spread details can be viewed. 
	
- In the 
	Forecast Spread Details 
	window, in No. of 
	Periods field of the Display Properties set of fields use the 
	arrows to modify the number of periods for which the cost/revenue spread  
	should be displayed.
- Modify the From and To Periods using the 
	arrows if required.
- Modify the cost/revenue in each accounting period if required 
	in Cost and/or Revenue tabs.
- Select the currency from the Display Currency list box in which the amounts should be 
	displayed.
- If a manual update of a period amount in 
	the window results in recalculating the period amounts of the same 
	period in other currencies, select the Update Other Currencies 
	checkbox.
- Click Save.