Start Rental
Explanation
This activity is used for starting a rental. Starting rental for a rental line typically indicates 
that the item is in operation, however, it could also mean that it the line is under transportation depending on the rental mode selected. In order for 
rental transactions to be generated for a rental line, rental has to be started 
for the line.
Rentals can be started in the Manage Rentals 
or the  Rental Workbench windows. As 
rental is started, a default mode (with corresponding price factor) will be 
suggested. This may be changed by the user as required.
For the Rent In and Rent Out processes, there is also 
an option to start rental automatically as follows. In both cases, the Rental 
Mode that is set as default will be used.
	- Rent In: When receiving the items for the purchase 
	order, there is an option in the receipt dialog box to automatically start 
	rental, allowing the user to specify the start rental date.
- Rent Out: By setting the Start Rental option on 
	the customer order rental line to Use Planned Rental Start Date/Time or 
	Use Actual Ship Date/Time, rental will automatically be started as items 
	are delivered for the line.
For the Project Charging/Rent to Projects 
functionality, rental can also be started from the demand line itself by 
right-clicking and clicking Start Rental.
For the Work Order Charging/Rent to Work Order 
functionality, rental can also be started from the Tool and 
Facility line itself 
by right-clicking and clicking Start Rental.
Prerequisites
A rental line has to have been created. Additionally 
there are some requirements depending on the rental type as follows:
	- Rent In: For a rented in purchase order line, rental 
	can be started for non-tracked parts once the purchase order has been set to 
	the Released status. For tracked parts (lot batch and/or serial-tracked), 
	rental can only be started once the specific lot batch or serial number has been 
	assigned and received.
- Rent Out: To start rental for a rented out customer 
	order line, the customer order has to be in the Released status and there 
	has to be reserved items for the relevant line.
- Project Charging: To start rental for a project 
	charging line when using your internal asset pool, the project activity has 
	to be in the Released status and there has to be reserved items for 
	the relevant line. When renting in specifically to the project, see the Rent 
	In 
	prerequisites above.
- Work Order Charging: To start rental for a 
	tool and facility line with rental supply option Internal Charging, the 
	items have to be reserved or issued to the corresponding material line of 
	the work order.
System Effects
By starting rental for a line, rental transactions will 
be generated for the line when running the Generate Rental Transactions task, 
provided there is a valid schedule for the line.
Window
Manage Rentals 
Rental Workbench
Register Purchase Order Arrivals 
Customer Order 
Project Navigator/Demand/Misc. Rental Parts
Prepare Work Order/Tools and Facilities
Related Window Descriptions
Manage Rentals
Rental Workbench
Register 
Purchase Order Arrivals 
Customer Order 
Project Navigator/Demand/Misc. Rental Parts
Start Rental/ Create Manual Event/ End Rental
Prepare Work Order/Tools and Facilities  
Procedure
	- Open the Manage Rentals window.
- Query for the rental that needs to be started, in 
	the Rental No field.
- Select the record, right-click and click Start Rental.
- Enter the event date and time that the rental 
	should be ended, in the respective fields.
- Optionally enter a note to be saved in the event 
	history.
- In the table part of the dialog box, select the 
	quantity to end rental for.
- If required, adjust the values in the Mode and 
	Price Factor fields.
- Click OK.