Assign Mitigating Actions
Explanation
This activity is used to define actions on a particular risk analysis record. 
Actions describe what has to be done to handle the risk, by whom and by when. 
The purpose of this activity is to assign and track tasks against individuals. 
Prerequisites
A response record must exist for the risk analysis in mind. 
System Effects
None. 
Window
Risk Actions
Risk Action
Risk Analysis Navigator
Related Window Descriptions
Risk Actions
Risk Action
Risk Analysis Navigator/Action List
Procedure
Use the following procedure to define mitigating actions on a particular risk 
record: 
	- Open the 
	Risk Analysis Navigator window and click on the 
	
	Action List tab, or open the 
	
	Risk Actions or the 
	Risk Action 
	windows. Note: If you use the 
	Action List tab on the 
	Risk Analysis Navigator window, navigate to and select the response 
	node a selected risk analysis to add an action.
- Click New (F5) to create a new record. A risk action is 
	created with Status New.  
- In the Response ID field, use the List of Values to select a 
	response record that you want to connect the action to. Note: If you 
	use the 
	Action List tab on the 
	Risk Analysis Navigator 
	window, this field will not be displayed on this tab.
- In the Action Description field, enter a description that 
	explains the possible response that can be taken. 
- In the Action Assigned field, use the List of Values to select a 
	person to whom the action should be assigned. 
- In the Action Date field, enter the date by which the action 
	should be completed. 
- For the Action Status field, select the status that you want to 
	assign to the particular action record. 
- In the Action Note field, enter any notes that you want to add 
	about the action. 
- Click Save.