Define Consequences
Explanation
This activity is used to establish the probable consequences or effects 
of a known set of problems. On defining a set of consequences, probability and 
impact estimates are made which then calculate risk severity and potential risk exposure. 
Entries can be made for Cost, Time or both. Additional consequences can be 
registered against categories which are less standard than the usual Cost and 
Time, for example, Environmental or Reputation Risk. 
Probability estimates can be made using a rating selection such as High, Medium, 
Low which is converted into a percentage for the system calculations. Where 
there is more accurate data available, the user can alternatively choose to 
enter a percentage value - the system then selects the relevant rating selection 
from the base data. 
Similarly, the cost impact can be entered using a simple rating selection or 
else a numerical value in the risk currency can be entered. 
Prerequisites
A parent problem record must exist. 
System Effects
	- When both probability and impact have been entered, the 
system is able to assess the potential risk exposure. 
- A risk severity rating, if defined, helps to prioritize the risks for 
	action.
Window
Risk Analysis Navigator
Risk Consequences
Risk Consequence
Related Window Descriptions
Risk 
Analysis Navigator/Consequence List
Risk Consequences
Risk Consequence
Procedure
Use the following procedure to define consequences on a problem using the 
Risk Analysis Navigator/Consequence List tab. 
Note: You can also use the 
Risk Consequences 
	or Risk Consequence 
	windows to perform this activity in which case the relevant parent records,
Analysis ID and Problem ID, must be selected. Field entry rules 
are the same as those defined for the 
Risk Analysis Navigator window.
	- Navigate to and select the problem node for the risk analysis to add a consequence. 
- Click New (F5) to 
	create a new record. A default value for Consequence ID will appear 
	for this record, which can be modified if required, to change the display 
	sequence.
- In the Consequence Description field, enter a description of the 
	effect that may occur. A value for this field is required. 
- In the Probability Percentage field, enter the expected 
	probability of a consequence happening or else select the Probability 
	Level ID from the List of Values. 
- For the Cost Impact estimate, enter either estimates cost values or 
	choose a Cost Impact Level from the List of Values. A value 
	for Total Base Cost must exist before any cost values or cost impact level can be set.
- In the Most Likely Cost Estimate field, enter the cost impact 
	value most likely expected as a result of the consequence occurring. Note: 
	If the 3 - Point Analysis method is used, the Min Cost and Max Cost fields 
	must also have values entered on them in order to calculate the weighted 
	average. 
- Entry of potential time delay needs the Most Likely value for the 
	selected time unit. As for cost entry, use of 3 - Point analysis method 
	requires that Min and Max fields are also entered. 
- Click Save.