Enter Performed Interval Based Maintenance
Explanation
This activity is used to enter interval based maintenance activities that 
have been previously performed on the serial structure, but not yet been logged 
in the system. You can enter this information for both components that have not 
been logged in the system before, and components that have existing, but not 
complete, historical data in the system. It is possible to adjust the values 
that were recently entered so that several records do not appear in the log by 
mistake. The 
 Component Life/Interval 
Maint tab displays all possible maintenance activities, not only 
those for which tasks have been created. The maintenance plan controls what is 
visible in this window for each selected serial. For more information, refer to
the online help file
Interval Based Maintenance Programs.
You cannot record an overhaul that has occurred between
existing operational log records or where the latest operational loggings have not been completed. 
However, as an exception, you will be allowed to report an overhaul prior to all 
the recorded operational loggings. It is necessary for all the logging dates of 
the latest logging to be the same for all operational parameters of the serial 
before you can report and overhaul from the Component Life 
window.
Prerequisites
	- Interval based maintenance (the maintenance plan) must have been set up 
	for all maintenance groups valid for the part number.
System Effects
  - Records are updated as if the maintenance activity had been signed off 
	through a work order, but without work orders being generated.
- An entry will be created for the serial in the interval maintenance 
	history.
- An entry in the serial order history will be added to store the 
	operational values according to ordinary data entry. If this is ordinary 
	maintenance, a record will be added to the maintenance log for the serial. 
	If the maintenance is an overhaul, records will be added in both the 
	maintenance log and the operational log. 
Window
Component Life
Related Window Descriptions
Component Life/Interval Maint
Procedure
This section is divided into different subsections in 
order to describe the different ways of entering performed interval based 
maintenance depending on how the maintenance plan has been set up. Each 
subsection will have a defined scenario containing at least what the maintenance 
plan looks like. In addition to the maintenance plan, the average operational 
values (per month) and the current operational log values will influence the 
result of entering the performed interval based maintenance.
All the different subsections are referred to as different 
cases:
Common steps relevant for all subsections
  - Open the 
	Component Life window, and query 
	(F3) for the necessary serial structure.
  
- Click the 
	Interval Maint tab, and observe 
	the maintenance codes that appear automatically.
- For the maintenance task to be logged, enter a value in the
    Value At Maintenance field for the primary operational parameter in 
	the upper part of the window. 
- In the lower part of the window, enter a value in the 
  Value At Maintenance field for the other operational parameters.
- Repeat steps 3 and 4 for other maintenance tasks to be logged.
Common information used by all subsections
  - Valid operational parameters:
  
    | Operational Parameter | Description | Average Value (per month) | 
  
    | FHR | Flight Hours | 50 | 
  
    | LDG | Landings | 20 | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning):
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | A | 200 | FHR | - | - | 200 | - | - | Inspection | No Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example: 
  
    | Date | Value | 
  
    | April 10th 2004 | 3190 FHR | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code A.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value at Maintenance field enter 3190 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 3190 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 3200 is automatically populated in 
	the Maint Interval field. This value tells the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. No tolerances have been defined for this 
	maintenance code, which means that all due values are presented from the 
	nominal values from the maintenance plan (in this case 200, 400, 600, etc.):
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | A | 3400 | FHR | September 15th 
	2004 | September 15th 
	2004 | September 16th 
	2004 | Interval | 
  
    | A | 3600 | FHR | January 13th 2005 | January 13th 2005 | January 14th 2005 | Interval | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters are entered 
	in the lower part of the 
	Maintenance Plan/Intervals tab as 
	this is a secondary operational parameter:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | A1 | 160 | LDG | - | - | 160 | - | - | Inspection | No Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example: 
  
    | Date | Value | 
  
    | February 10th 
	2004 | 1450 LDG 3050 FHR | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code A1.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's interval defined in a 
	secondary operational parameter, but since the serial also have a value for 
	the primary operational parameter at the time of the maintenance, this must 
	be entered.
    
- In the Value at Maintenance (for operational 
	parameter FHR) field enter the actual value at the time the maintenance was 
	performed, for instance 3050.
    
- In the Value Total field enter the actual 
	value at the time the maintenance was performed, for instance 3050.
    
- Save the record (F12). 
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 1450 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1450 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 1440 is automatically populated in 
	the Maint Interval field. This value "tells" the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. No tolerances have been defined for this 
	maintenance code, which means that all due values are presented from the 
	nominal values from the maintenance plan (in this case 160, 320, 480, etc.):
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | A1 | 1600 | LDG | August 16th 2004 | August 16th 2004 | August 17th 2004 | Interval | 
  
    | A1 | 1760 | LDG | April 13th 2005 | April 13th 2005 | April 14th 2005 | Interval | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning):
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | A2 | - | - | 150 | Days | - | 150 | Days | Inspection | No Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in this example:
  
    | Date | Value | 
  
    | March 3rd 2004 | 3125 FHR | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code A2.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value at Maintenance (for operational 
	parameter FHR) field enter the actual value at the time the maintenance was 
	performed, for instance 3125.
    
- In the Value Total field enter the actual 
	value at the time the maintenance was performed, for instance 3125.
    
- In the Calendar Interval field use the List of 
	Values to select value 150 d. Observe that Calendar Unit is 
	automatically populated.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | A2 | 3320 (approx.) | FHR | July 31st 2004 | July 31st 2004 | August 1st 2004 | Calendar | 
  
    | A2 | 3570 (approx.) | FHR | December 28th 
	2004 | December 28th 
	2004 | December 29th 
	2004 | Calendar | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters for the 
	secondary operational parameters are entered in the lower part of the 
	
	Maintenance Plan/Intervals tab:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | A3 | 200 | FHR | 150 | Days | 200 | 150 | Days | Inspection | No Cycle | - | - | 
  
    |  | 80 | LDG | - | - | 80 | - | - | - | - | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example: 
  
    | Date | Value | 
  
    | April 7th 2004 | 3170 FHR 1517 LDG | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code A3.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's intervals defined in 
	multiple parameters (including calendar time) which means that a value has 
	to be entered for all the intervals using the nominal value. In this 
	particular case it was the LDG interval that triggered the execution of the 
	maintenance.
    
- In the Value at Maintenance field enter 3170 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 3170 (which is 
	the value when the maintenance was performed).
    
- Observe that value 3200 is automatically populated in 
	the Maint Interval field. Change this value to 3800 which is 
	equivalent to the 1520 LDG interval that will be entered later (19 times the 
	initial interval).
    
- In the Calendar Interval field use the List of 
	Values to select value 150 d. Observe that Calendar Unit is 
	automatically populated.
    
- Save the record (F12).
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 1517 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1517 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 1520 is automatically populated in 
	the Maint Interval field.
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. No tolerances have been defined for this 
	maintenance code, which means that all due values are presented from the 
	nominal values from the maintenance plan (in this case 80, 160, 240, etc.):
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | A3 | 1600 | LDG | August 16th 2004 | August 16th 2004 | August 17th 2004 | Interval | 
  
    | A3 | 1680 | LDG | December 14th 
	2004 | December 14th 
	2004 | December 15th 
	2004 | Interval | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning):
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | B | 200 | FHR | - | - | 200 | - | - | Inspection | No Cycle | 10% | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Date | Value | 
  
    | April 8th 2004 | 3175 FHR | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code B.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value at Maintenance field enter 3175 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 3175 (which is 
	the value when the maintenance was performed).
    
- Observe that the value -25 is automatically populated 
	in the Correction Value field. The reason for this is that tolerances 
	are defined, and the maintenance is performed outside the tolerances (20 
	FHR). This value will ensure that the next occurrence of this maintenance 
	code is due 25 FHR earlier.
    
- Ensure that value 3200 is automatically populated in 
	the Maint Interval field. This value "tells" the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B | 3375 | FHR | August 31st 2004 | August 31st 2004 | September 1st 
	2004 | Interval | 
  
    | B | 3575 | FHR | December 29th 
	2004 | December 29th 
	2004 | December 30th 
	2004 | Interval | 
  
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters are entered 
	in the lower part of the 
	Maintenance Plan/Intervals tab as 
	this is a secondary operational parameter:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | B1 | 160 | LDG | - | - | 160 | - | - | Inspection | No Cycle | 10% | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example: 
  
    | Date | Value | 
  
    | January 5th 2004 | 1420 LDG 2950 FHR | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code B1.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's interval defined in a 
	secondary operational parameter, but since the serial also have a value for 
	the primary operational parameter at the time of the maintenance, this must 
	be entered.
    
- In the Value at Maintenance (for operational 
	parameter FHR) field enter the actual value at the time the maintenance was 
	performed, for instance 2950.
    
- In the Value Total field enter the actual 
	value at the time the maintenance was performed, for instance 2950.
    
- Save the record (F12).
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 1420 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1420 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 1440 is automatically populated in 
	the Maint Interval field. This value "tells" the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- Observe that the value -20 is automatically populated 
	in the Correction Value field. The reason for this is that tolerances 
	are defined, and the maintenance is performed outside the tolerances (16 LDG). 
	This value will ensure that the next occurrence of this maintenance code is 
	due 20 LDG earlier.
  - Expected output when the due calculation is executed 
	June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B1 | 1580 | LDG | July 17th 2004 | July 17th 2004 | July 18th 2004 | Interval | 
  
    | B1 | 1740 | LDG | March 14th 2005 | March 14th 2005 | March 15th 2005 | Interval | 
  
	- Maintenance Plan (all maintenance codes have 10 
	days forewarning). 
  
    | Maintenance Code | Calendar Interval | Calendar Unit | Recurring Calculation | Recurring Calendar Interval | Recurring Calendar Unit | Calendar Interval - Adjust if done early | Calendar Interval - Adjust if done late | Calculation Rule | Cycle | 
  
    | B2 | 150 | Days | Yes | 150 | Days | No | Yes | Inspection | No Cycle | 
  
    | B3 | 150 | Days | Yes | 150 | Days | Yes | Yes | Inspection | No Cycle | 
  
    | B4 | 150 | Days | Yes | 150 | Days | No | No | Inspection | No Cycle | 
  
    | B5 | 150 | Days | Yes | 150 | Days | Yes | No | Inspection | No Cycle | 
  
	- Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
	- Last Performed Maintenance for 
	the maintenance code in this example:
  
    | Date | Value | 
  
    | February 1st 2004 | 3000 FHR | 
  
Combination 1 - How to enter performed interval maintenance 
for maintenance plans that have the Cal Int. - Adjust if done Late check 
box selected:
	
		- Locate the record with Maint Code B2.
		
- In the 
		Maint Date
      	field, enter the maintenance date.
		
- In the Value at Maintenance 
		field, enter 3000 
	(which is the value when the maintenance was performed).
		
- In the Value Total field, enter 
		3000 (which is 
	the value when the maintenance was performed).
		
- In the Calendar Correction field, enter 
		-10. Note that this value should always be a negative value since 
		the maintenance has been done late.
- Save the record (F12).
	- Expected output when the due calculation is executed 
	on June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B2 | 3255 | FHR | June 20th 2004 | June 20th 2004 | June 21sr 2004 | Calendar | 
  
    | B2 | 3505 | FHR | November 17th 
	2004 | November 17th 
	2004 | November 18th 
	2004 | Calendar | 
  
Combination 2 - How to enter performed interval 
maintenance for maintenance plans that have both the Cal 
Int. - Adjust if done Early and Cal Int. - Adjust if done Late check 
boxes selected:
	
		- Locate the record with Maint Code B3.
- 
		In the 
		Maint Date
      	field, enter the maintenance date.
		
- In the Value at Maintenance 
		field, enter 3000 
	(which is the value when the maintenance was performed).
		
- In the Value Total field, enter 
		3000 (which is 
	the value when the maintenance was performed).
		
- In the Calendar Correction field, enter 
		10 and/or -10. 
- Save the record (F12).
	- Expected output when the due calculation is executed 
	on June 17th 2004: (Note: The following tables display the expected 
	output when maintenance is done 10 days early and 10 days late respectively.)
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B3 | 3282 | FHR | July 7th 2004 | July 7th 2004 | July 8th 2004 | Calendar | 
  
    | B3 | 3532 | FHR | December 7th 2004 | December 7th 2004 | December 8th 2004 | Calendar | 
  
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B3 | 3255 | FHR | June 20th 2004 | June 20th 2004 | June 21st 2004 | Calendar | 
  
    | B3 | 3505 | FHR | November 17th 
	2004 | November 17th 
	2004 | November 18th 
	2004 | Calendar | 
  
Combination 3 - How to enter performed interval 
maintenance for maintenance plans that do not have the Cal 
Int. - Adjust if done Early and Cal Int. - Adjust if done Late check 
boxes selected:
	
		- Locate the record with Maint Code B4.
- 
		In the 
		Maint Date
      	field, enter the maintenance date.
		
- In the Value at Maintenance 
		field, enter 3000 
	(which is the value when the maintenance was performed).
		
- In the Value Total field, enter 
		3000 (which is 
	the value when the maintenance was performed).
		
- Note that you cannot enter a value in the Calendar Correction 
		field since settings for tolerances (i.e., 
		adjustments when maintenance is performed early or late) has not been 
		defined on the maintenance plan.
- Save the record (F12).
	- Expected output when the due calculation is executed on June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B4 | 3271 | FHR | June 30th 2004 | June 30th 2004 | July 1st 2004 | Calendar | 
  
    | B4 | 3521 | FHR | November 17th 
	2004 | November 17th 
	2004 | November 18th 
	2004 | Calendar | 
  
Combination 4 - How to enter performed interval 
maintenance for maintenance plans that have the Cal Int. - 
Adjust if done Early check box selected:
	
		- Next, locate the record with Maint Code B5.
- 
		In the 
		Maint Date
      	field, enter the maintenance date. 
		
- In the Value at Maintenance 
		field, enter 3000 
	(which is the value when the maintenance was performed).
		
- In the Value Total field, enter 
		3000 (which is 
	the value when the maintenance was performed).
		
- In the Calendar Correction field, enter 
		10. Note that this value should always be a 
		positive value since the maintenance has been done early.
- 
		Save the record (F12).
	- Expected output when the due calculation is executed 
	on June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B5 | 3282 | FHR | July 7th 2004 | July 7th 2004 | July 8th 2004 | Calendar | 
  
    | B5 | 3532 | FHR | December 7th 2004 | December 7th 2004 | December 8th 2004 | Calendar | 
  
	
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters for the 
	secondary operational parameters are entered in the lower part of the 
	
	Maintenance Plan/Intervals tab:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | B6 | 200 | FHR | 150 | Days | 200 | 150 | Days | Inspection | No Cycle | 10% | - | 
  
    |  | 80 | LDG | - | - | 80 | - | - | - | - | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Date | Value | 
  
    | March 25th 2004 | 3152 FHR 1502 LDG | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code B6.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's intervals defined in 
	multiple parameters (including calendar time) which means that a value has 
	to be entered for all the intervals using the nominal value. In this 
	particular case it was the LDG interval that triggered the execution of the 
	maintenance.
    
- In the Value at Maintenance field enter 3152 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 3152 (which is 
	the value when the maintenance was performed).
    
- Observe that value 3200 is automatically populated in 
	the Maint Interval field. Change this value to 3800 which is 
	equivalent to the 1520 LDG interval that will be entered later (19 times the 
	initial interval).
    
- Enter value -648 in the Correction Value
      field. The reason for this is that tolerances are defined, and the 
	maintenance is performed outside the tolerances (20 FHR).
    
- In the Calendar Interval field use the List of 
	Values to select value 150 d. Observe that Calendar Unit is 
	automatically populated.
    
- Save the record (F12).
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 1502 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1502 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 1520 is automatically populated in 
	the Maint Interval field.
    
- Observe that the value -18 is automatically populated 
	in the Correction Value field. The reason for this is that tolerances 
	are defined, and the maintenance is performed outside the tolerances (8 LDG). 
	This value will ensure that the next occurrence of this maintenance code is 
	due 18 LDG earlier.
  - Expected output when the due calculation is executed 
	June 17th 2004:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | B6 | 1582 | LDG | July 20th 2004 | July 20th 2004 | July 21st 2004 | Interval | 
  
    | B6 | 1662 | LDG | November 17th 
	2004 | November 17th 
	2004 | November 18th 
	2004 | Interval | 
  
In this case the use of an overhaul (with cycle) is used. 
The reason for this is that non-recurring maintenance will only be executed once 
if not combined with an overhaul in the maintenance plan. Entering values for 
performed interval maintenance, with or without an overhaul, is exactly the same 
with the exception that without an overhaul there will not be any due dates 
calculated.
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning):
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | C | 1000 | FHR | - | - | - | - | - | Inspection | No Cycle | - | - | 
  
    | OH | 4000 | FHR | - | - | - | - | - | Overhaul | Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Maintenance Code | Maintenance Date | Value | Comment | 
  
    | C | June 1st 1999 | 1000 FHR |  | 
  
    | OH | January 1st 1998 | 0 FHR | This maintenance has never been performed. A starting 
	point must be set. | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code C.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value at Maintenance field enter 1000 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1000 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 1000 is automatically populated in 
	the Maint Interval field. This value tells the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- Find the record with Maint Code OH.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value Total field enter 0.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. This maintenance is due 1000 FHR after 
	the next OH:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | OH | 4000 | FHR | September 10th 
	2005 | September 10th 
	2005 | September 11th 
	2005 | Interval | 
  
    | C | 1000 | FHR | May 3rd 2007 | May 3rd 2007 | May 4th 2007 | Interval | 
  
In this case the use of an overhaul (with cycle) is used. 
The reason for this is that non-recurring maintenance will only be executed once 
if not combined with an overhaul in the maintenance plan. Entering values for 
performed interval maintenance, with or without an overhaul, is exactly the same 
with the exception that without an overhaul there will not be any due dates 
calculated.
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters are entered 
	in the lower part of the 
	Maintenance Plan/Intervals tab as 
	this is a secondary operational parameter:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | C2 | 500 | LDG | - | - | - | - | - | Inspection | No Cycle | - | - | 
  
    | OH | 4000 | FHR | - | - | - | - | - | Overhaul | Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Maintenance Code | Maintenance Date | Value | Comment | 
  
    | C2 | June 1st 2000 | 500 LDG 1200 FHR |  | 
  
    | OH | January 1st 1998 | 0 FHR | This maintenance has never been performed. A starting 
	point must be set. | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code C2.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's interval defined in a 
	secondary operational parameter, but since the serial also have a value for 
	the primary operational parameter at the time of the maintenance, this must 
	be entered.
    
- In the Value at Maintenance (for operational 
	parameter FHR) field enter the actual value at the time the maintenance was 
	performed, for instance 1200.
    
- In the Value Total field enter the actual 
	value at the time the maintenance was performed, for instance 1200.
    
- Save the record (F12).
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 500 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 500 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 500 is automatically populated in 
	the Maint Interval field. This value "tells" the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- Save the record (F12).
- Find the record with Maint Code OH.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value Total field enter 0.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. This maintenance is due 500 LDG after the 
	next OH:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | OH | 4000 | FHR | September 10th 
	2005 | September 10th 
	2005 | September 11th 
	2005 | Interval | 
  
    | C2 | 500 | LDG | September 10th 
	2007 | September 10th 
	2007 | September 11th 
	2007 | Interval | 
  
In this case the use of an overhaul (with cycle) is used. 
The reason for this is that non-recurring maintenance will only be executed once 
if not combined with an overhaul in the maintenance plan. Entering values for 
performed interval maintenance, with or without an overhaul, is exactly the same 
with the exception that without an overhaul there will not be any due dates 
calculated.
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning):
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | C3 | - | - | 1000 | Days | - | - | - | Inspection | No Cycle | - | - | 
  
    | OH | 4000 | FHR | - | - |  | - | - | Overhaul | Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Maintenance Code | Maintenance Date | Value | Comment | 
  
    | C3 | September 27th 
	2000 | 1300 FHR |  | 
  
    | OH | January 1st 1998 | 0 FHR | This maintenance has never been performed. A starting 
	point must be set. | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code C3.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value at Maintenance field enter 1300 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1300 (which is 
	the value when the maintenance was performed).
    
- In the Calendar Interval field use the List of 
	Values to select value 1000 d. Observe that Calendar Unit is 
	automatically populated.
    
- Find the record with Maint Code OH.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value Total field enter 0.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004 is available below. This maintenance is due 1000 days after 
	the next OH:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | OH | 4000 | FHR | September 10th 
	2005 | September 10th 
	2005 | September 11th 
	2005 | Interval | 
  
    | C3 | 1667 (approx.) | FHR | June 6th 2008 | June 6th 2008 | June 7th 2008 | Calendar | 
  
In this case the use of an overhaul (with cycle) is used. 
The reason for this is that non-recurring maintenance will only be executed once 
if not combined with an overhaul in the maintenance plan. Entering values for 
performed interval maintenance, with or without an overhaul, is exactly the same 
with the exception that without an overhaul there will not be any due dates 
calculated.
  - Maintenance Plan (all maintenance codes have 10 days 
	forewarning). Observe that intervals and operational parameters for the 
	secondary operational parameters are entered in the lower part of the 
	
	Maintenance Plan/Intervals tab:
  
    | Maintenance Code | Maintenance Interval | Operational Parameter | Calendar Interval | Calendar Unit | Recurring Interval | Recurring Calendar Interval | Recurring Calendar Unit | Calculation Rule | Cycle | Lower Tolerance | Upper Tolerance | 
  
    | C4 | 2000 | FHR | 30 | Months | - | - | - | Inspection | No Cycle | - | - | 
  
    |  | 900 | LDG | - | - |  | - | - | - | - | - | - | 
  
    | OH | 4000 | FHR | - | - | - | - | - | Overhaul | Cycle | - | - | 
  
  - Last Operational Logging:
  
    | Operational Parameter | Last To Date | Value After Overhaul | Value Total | 
  
    | FHR | May 1st 2004 | 3250 | 3250 | 
  
    | LDG | May 1st 2004 | 1560 | 1560 | 
  
  - Last Performed Maintenance for the maintenance code in 
	this example:
  
    | Maintenance Code | Maintenance Date | Value | Comment | 
  
    | C4 | June 19th 2000 | 1230 FHR 507 LDG |  | 
  
    | OH | January 1st 1998 | 0 FHR | This maintenance has never been performed. A starting 
	point must be set. | 
  
  - How to enter performed interval maintenance for this 
	case:
  
    - Find the record with Maint Code C4.
    
- Enter the maintenance date into the Maint Date
      field.
    
- This maintenance code has it's intervals defined in 
	multiple parameters (including calendar time) which means that a value has 
	to be entered for all the intervals using the nominal value. In this 
	particular case it was the LDG interval that triggered the execution of the 
	maintenance.
    
- In the Value at Maintenance field enter 1230 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 1230 (which is 
	the value when the maintenance was performed).
    
- Observe that value 2000 is automatically populated in 
	the Maint Interval field. This value "tells" the application where in 
	the maintenance plan the serial is currently located, and will be the basis 
	for the value of the next maintenance.
    
- In the Calendar Interval field use the List of 
	Values to select value 30 months. Observe that Calendar Unit is 
	automatically populated.
    
- Save the record (F12).
- Find Oper Param LDG in the lower table of the 
	window.
    
- In the Value at Maintenance field enter 507 
	(which is the value when the maintenance was performed).
    
- In the Value Total field enter 507 (which is 
	the value when the maintenance was performed).
    
- Ensure that value 900 is automatically populated in 
	the Maint Interval field.
    
- Save the record (F12).
- Find the record with Maint Code OH.
    
- Enter the maintenance date into the Maint Date
      field.
    
- In the Value Total field enter 0.
    
- Save the record (F12).
  - Expected output when the due calculation is executed 
	June 17th 2004  is available below. This maintenance is due 30 months 
	after the next OH:
  
    | Maintenance Code | Planned Value | Operational Parameter | Due Date | Planned Date From | Planned Date To | Calculation Type | 
  
    | OH | 4000 | FHR | September 10th 
	2005 | September 10th 
	2005 | September 11th 
	2005 | Interval | 
  
    | C4 | 1500 (approx.) | FHR | February 27th 
	2008 | February 27th 
	2008 | February 28th 
	2008 | Calendar |