Complete Sub Contract
Explanation
This activity is used to complete a sub contract. It is possible to complete the sub contract even if a released call off still 
exists for a line item, i.e., the contractor has decided that he or she no 
longer intends to proceed with the call off. In this case, the status of the 
line item will remain in the Work In Progress status.
Once a sub contract is completed, it is no longer allowed to create new 
revisions, new valuations or modify data on this contract.
Prerequisites
  - The sub contract must be in the Active status.
System Effects
  - The status of the sub contract is set to Completed.
- New valuations cannot be created for this contract while it is in the 
	completed state.
Window
Sub Contract
Sub Contracts
Related Window Descriptions
Sub Contract
Sub Contracts 
Procedure
  - Open the 
	Sub Contract window or the 
	Sub Contracts window.
- Query (F3) for the necessary sub contract.
- Right-click anywhere in the header, point to Status, and then 
	click Complete.
- A message requiring approval of the step appears, click Yes.