Allocate Resource
Explanation
Use this activity to allocate maintenance employees and/or tools an facilities 
required to execute a work order and/or work order operations. 
This activity is typically used when;
	- Allocating a maintenance employee to execute a work order.
- Allocating one or several maintenance employees to execute a work order 
	operation
- Allocating one or several tool and facilities required to execute a work 
	order
- Allocating one or several tool & facilities required to execute a work 
	order operation
Prerequisites
	- Maintenance organizations must be defined Organization Basic Data.
- Maintenance employees must exist in Organization 
	Basic Data.
- Tools and facilities must exist in Tools & 
	Facilities Basic Data.
- Execution time and/or planned hours , planned men must be defined in on 
	the work order/work order operation.
- Planned hours and planned quantity must be defined on tool/facility rows.
System Effects
Allocating a maintenance employee to work order
As a result of this activity, 
the entire work order will be allocated to a single maintenance employee. A work 
order level allocation will be created using a default operation with the 
operation no "0" (which is hidden and hence not visible from the 
operations tab) and also an allocation with Allocation From and Allocation To will be created against the 
selected employee and the selected work order.  The work order will be set 
to  Operations follow Work Order Status. Furthermore the 
allocated 
employee signature will be set in  
Executed by, the 
 Fixed Executed by flag 
will be checked and the selected start date of the allocation will be inserted 
into the  Fixed Start Date. If there are 
operations present on the work 
order these will also be allocated to the executed by on the work order. These 
allocations will however not receive any  Allocation From and Allocation To
or any Allocated Hours since all the allocated hours will be allocated to the default 
work order operation no "0" 
(again please note that the default operation "0" and its allocation will no be 
visible from the operations tab).
Allocating one or several maintenance employees to 
execute a work order operation
As a result of this activity, one or several multi-line 
level allocations with an Allocation From and Allocation To will 
be created against the selected employee/employees and the selected operation.
Allocating one or several tool & facilities required to 
execute a work order or a work order operation
As a result of this activity, one or several allocations with Allocation From and 
Allocation To will be created against the selected tool & facility and the 
selected work order/operation. 
Window
Allocate Resource
Related Window Descriptions
Allocate Resource
Resource Allocation Search
Legend
Procedure
Follow this procedure to allocate a maintenance employee to a work order or a 
route work order:
	- Right-Click on a record in Active Work Orders, Active 
	Routes or on the header in Service Request, 
	Prepare Work Order, Report in Route window and select
	Allocate Resource… . 
- This will open the Allocate Resource… dialog.
- Maintenance employees that matches the criteria’s of the selected work 
	order will now be displayed in the lower pane together with their current 
	schedules and allocations. If there are operations defined on the work order with 
	multiple different Maintenance Organizations, Teams or Crafts defined then the 
	work order operations must be allocated to 
	several different employees and the work order can therefore not be 
	allocated to one single maintenance employee. However if the operations all 
	have the same Maintenance Organizations, Teams or Crafts 
	defined, then it will be possible to allocate 
	all the operations to one single maintenance employee  selecting the 
	option "All".
- Select the work order allocation and drag it to the desired slot in a 
	resource's schedule.
- In order to adjust the duration of the allocation, select the allocation 
	drag either of the ends of the allocations to extend the allocation 
	backwards or forwards in time.
- If there is no maintenance 
	employees available in the Maintenance organization and/or Team 
	specified on the work order that matches the Craft, License 
	and/or Competency requirements for the work order, the user can press 
	the search button and in the search dialogue and modify the search criteria 
	in to search in other Maintenance organizations/Teams and or 
	to change the Craft/License/Competency requirements. 
	(For more detailed information on how to change the search criteria's see 
	instructions in section "change search criteria" below.)
- If the Requested Start, Late Start, Fixed Start or
	Requested Finish has been set on the work order and  there
	is no available time slot that complies with these 
	dates, then the user may search again by pressing "Search" button and ticking the checkbox "Ignore Constraints. This action 
	will disable the constraining dates. 
- If there is no Employee available with a free slot in his/her schedule 
	or according to schedule, then the user may search again by ticking the 
	checkboxes "Show All" and/or "Exclude Schedules"
 "Show All" will show all 
	Employees even tough they are already busy during 
	the time. "Exclude Schedule" will show all Employees even tough they might 
	not be available according to schedule or do not have a valid schedule 
	during that time.
- Click Save.
The work order will be set to Operations follow Work Order 
Status. Furthermore the allocated employee will be set in Executed by, the 
Fixed 
Executed by flag will be "checked”
and the start time of the allocation start will be inserted into the Fixed Start 
Date. A work order level allocation 
will be created using a default operation with the 
operation no "0"  and also an allocation with Allocation From and Allocation To will be created against the 
selected employee for the selected work order. If there are operations present on the 
work 
order these will also be allocated to the executed by on the work order. These 
allocations will however not receive any  Allocation From and Allocation To
or any Allocated Hours since 
all the allocated hours will be allocated for the default work order operation no "0".
Follow this procedure to allocate one or several maintenance employees to a work 
order 
operation:
	- Right-Click in the header of Service 
	Request or Prepare Work Order or select one or several an individual 
	operations in the Job/Operations tab or the Operations tab in 
	Prepare Work 
	Order and select Allocate Resource… . 
- The Allocate Resource…
	dialog will 
	open.
- Maintenance employees that matches the criteria’s of the selected 
	operation's will now be displayed in the lower pane together with their 
	current schedules and allocations. 
- Select the operation allocation/allocation's and drag it to the desired 
	slot in a resource's schedule. (If there  is a requirement for multiple 
	persons the several bars will appear, the user will then have to drag and 
	drop several times) 
- In order to adjust the duration of the allocation, select the allocation 
	and 
	drag either of the ends of the allocations to extend the allocations 
	backwards or forwards in time.
- If there is no maintenance 
	employees available in the Maintenance organization and/or Team 
	specified on the work order that matches the Craft, License 
	and/or Competency requirements for the work order, the user can press 
	the search button and in the search dialogue and modify the search criteria 
	in to search in other Maintenance organizations/Teams and or 
	to change the Craft/License/Competency requirements. 
	(For more detailed information on how to change the search criterias see 
	instructions in section "change search criteria" below.)
- If the Requested Start, Late Start, Fixed Start or
	Requested Finish has been set on the work order and  there
	is no available time slot that complies with these 
	dates, then the user may search again by pressing "Search" button and ticking the checkbox "Ignore Constraints. This action 
	will disable the constraining dates. 
- If there is no Employee available with a free slot in his/her schedule 
	or according to schedule, then the user may search again by ticking the 
	checkboxes "Show All" and/or "Exclude Schedules"
 "Show All" will show all 
	Employees even tough they are already busy during 
	the time. "Exclude Schedule" will show all Employees even tough they might 
	not be available according to schedule or do not have a valid schedule 
	during that time.
- Click Save.
One or several multi-line level allocations with an Allocation From and 
Allocation To, will now be created against the selected employees and 
the selected operations
Follow this procedure to allocate a tool/facility to a work order or work 
order operation: 
	- Navigate to Tools & Facilities tab in Prepare Work Order
	and select 
	Allocate Resource… for the lines you wish to allocate . The Allocate 
	Resource.. dialog will open.
- Tools and facilities that matches the criteria’s of the selected tool 
	and facilities row will now be displayed in the lower pane together with their 
	current schedules and allocations. 
- Select the tools and facilities allocation and drag it to a 
	slot in the desired schedule for the desired tool/facility. 
- In order to adjust the duration of the allocation, select the allocation 
	and drag either of the ends of the allocations to extend the allocations 
	backwards or forwards in time.
- If there is no maintenance 
	employees available in the Maintenance organization and/or Team 
	specified on the work order that matches the Craft, License 
	and/or Competency requirements for the work order, the user can press 
	the search button and in the search dialogue and modify the search criteria 
	in to search in other Maintenance organizations/Teams and or 
	to change the Craft/License/Competency requirements. 
	(For more detailed information on how to change the search criteria's see 
	instructions in section "change search criteria" below.)
- If the Requested Start, Late Start, Fixed Start or
	Requested Finish has been set on the work order and  there
	is no available time slot that complies with these 
	dates, then the user may search again by pressing "Search" button and ticking the checkbox "Ignore Constraints". This action 
	will disable the constraining dates. 
- If there is no Employee available with a free slot in his/her schedule 
	or according to schedule, then the user may search again by ticking the 
	checkboxes "Show All" and/or "Exclude Schedules"
 "Show All" will show all 
	Employees even tough they are already busy during 
	the time. "Exclude Schedule" will show all Employees even tough they might 
	not be available according to schedule or do not have a valid schedule 
	during that time.
- Click save.
A Tool/Facility ID will be set on the tool and facility line along 
with the selected Allocation From and Allocation To against the selected line. 
Follow this procedure to change 
search criteria's when querying for an Employee Resource:
	- In the Allocate Resource 
	dialog press the Search.. button.
- In the Site field, select the site to search within. Use the List 
	of Values to select a valid value.
- In the Maint Org field, select the maintenance organization to search within. 
	Use the List of Values to select a valid value.
- Select the Show All checkbox if resources that are already 
	allocated during the search period should be included in the search result.
	
- Select the Exclude Schedule checkbox if resources that are 
	not available during the search period should be included in the search 
	result.
- Select the Ignore Constraints checkbox if the constraining dates
	Requested Start, Late Start, Fixed Start or
	Requested Finish on the work order should be ignored when deciding 
	the search interval. 
- In the Team Site field, 
	enter the team site to search within. Use the List of Values to select a 
	valid value.
- In the Team field, 
	enter the team to search within. Use the List of Values to select a valid 
	value.
- In the Craft field, 
	enter the craft to search for. Use the List of Values to select a valid 
	value.
- Select the Include Sub Craft checkbox if resources that 
	have a craft that has been defined as a sub craft to the craft user is 
	searching for should be included in the search result. 
- Navigate to the Competency tab 
- Press the New button to add a new competency to the search 
	criteria's. To remove competencies press the Remove button.
- Press Save to save the changes.
- Navigate to the License tab 
- Press the New button to add a new competency to the search 
	criteria's. To remove licenses press the Remove button.
- Press Save to save the changes.
- Press Search to search
- Search results will be presented in Allocate Resource.
	
Follow this procedure to Change 
Search settings when querying for a Tool/Facility:
	- In the Allocate Resource 
	dialog press the Search.. button.
- In the Site field, select the site to search within. Use the List 
	of Values to select a valid value.
- In the Maint Org field, select the maintenance organization to search within. 
	Use the List of Values to select a valid value.
- Select the Show All checkbox if resources that are already 
	allocated during the search period should be included in the search result.
	
- Select the Exclude Schedule checkbox if resources that are 
	not available during the search period should be included in the search 
	result.
- Select the Ignore Constraints checkbox if the constraining dates
	Requested Start, Late Start, Fixed Start or
	Requested Finish on the work order should or should not constrain the 
	interval when the work order can be allocated when deciding the search 
	interval. 
- In the Tool/Facility Type  field, 
	enter the tool/facility type to search for. Use the List of Values to select 
	a valid value.
- Press Search to search
- Search Results will be presented in Allocate Resource.
	
Follow this procedure to change the Search Settings for Allocate 
Resource
	- In the Allocate Resource 
	dialog press the Search.. button.
- Navigate to the Settings tab 
- In the Show days Before field enter the number of days to display 
	before the search interval. Use the dropdown to select a valid value.
- In the Show days After field enter the number of days to display 
	before the search interval. Use the dropdown to select a valid value.
- In the Snap Time field enter the rounding in number of minutes 
	that should be used when the user drags and drops the allocation in the 
	Gantt or changes the duration of the allocation. Use the dropdown to select 
	a valid value.
- In the Population Fallback Period select the number of 
	days to search for, when no other end date constraint or planning end date 
	has been entered on the work order. Use the radio buttons to select the 
	number of days to use.
- Press Search to refresh Allocate Resource. The 
	settings will be stored in the user profile.
- Search results will be presented in Allocate Resource.   
	
Follow this procedure to view an 
explanation of symbols used in Allocate Resource. 
	- In the Allocate Resource 
	dialog press the Legend button.
- A legend with an explanation of 
	all symbols and colors used in Allocate Resource will be 
	shown.
- Press the "x" button to close 
	the Legend.