Alter Dependencies
Explanation
This activity is used to create or modify dependencies. 
Dependency relationships (predecessor - successor) can be created between the operations of a particular work order or 
between different work orders in the Execution Logic Structure (ELS). 
Dependencies cannot be created between operations of different work orders in 
the structure. If a work order does not contain any operations, dependencies 
cannot be created to this work order.
When 
creating or modifying dependencies using the Gantt chart, the Dependencies mode must be opened by 
right-clicking on the graph, and then clicking Create Dependencies Mode. 
In this mode you’ll see that the cursor becomes a pen, which can be used to draw 
the dependencies between different nodes in the structure.
You can also create 
dependencies by using the functionality included in the Predecessors 
dialog box or by using the List of Values function in the Predecessors 
and Successors sub tabs.
Prerequisites
	- The ELS must have been released, and the work 
	order ELS created.
- Work order operations must have been defined.
- The dependant work order must be in a status lower 
	than Started.
System Effects
	- Dependencies are created between two or more 
	operations of a work order.
- Dependencies are created between two or more work 
	orders in the structure.
Window
 
Work Order Execution 
Logic
Related Window Descriptions
Work Order Execution Logic  
Work Order Execution Logic/Gantt
Work Order Execution 
Logic/Dependencies/Predecessors 
Work Order Execution 
Logic/Dependencies/Successors 
Predecessors 
- Operation
Predecessors 
- Work Order
Procedure
Gantt chart
Use this procedure to create dependencies between the 
operations of a particular work order:
	- Open the Work Order Execution Logic 
	window and query for the desired work order or object ID.
- Click the Gantt tab.
- Right-click on the graph, and then click Create 
	Dependencies Mode.
- Draw dependencies between the operations of the 
	selected work order.
- Save the information (F12).
Use this procedure to create dependencies between work 
orders in the structure:
	- Open the Work Order Execution Logic 
	window and query for the desired work order or object ID.
- Click the Gantt tab.
- Right-click on the graph, and then click Create 
	Dependencies Mode.
- Draw dependencies between work orders.
- Save the information (F12).
Use this procedure to remove existing dependencies 
between operations or work orders.
	- Open the Work Order Execution Logic 
	window and query for the desired work order or object ID.
- Click the Gantt tab.
- Right-click on the dependency line, i.e., the 
	Black arrow, and then click Delete Link.
- Save the information (F12).
Predecessors sub tab
Use this procedure to define a predecessor for a 
certain operation:
	- Open the Work Order Execution Logic 
	window and query (F3) for the necessary work order or object ID.
- In the graphical object structure select the 
	operation for which you want to define a predecessor.
- Click the Dependencies tab and then 
	click the Predecessors sub tab.
- Create a new record (F5).
- In the Predecessor Operation No field, 
	enter the operation that is to be the predecessor. Use the List of Values to 
	select a valid value.
- Save the information (F12).
Use this procedure to define a predecessor for a 
certain work order:
	- Open the Work Order Execution Logic 
	window and query (F3) for the necessary work order or object ID.
- In the graphical object structure select the work 
	order for which you want to define a predecessor.
- Click the Dependencies tab and then 
	click the Predecessors sub tab.
- Create a new record (F5).
- In the Predecessor WO Number field, enter 
	the operation that is to be the predecessor. Use the List of Values to 
	select a valid value.
- Save the information (F12).
Successors sub tab
Use this procedure to define the successor for a 
certain operation:
	- Open the Work Order Execution Logic 
	window and query (F3) for the necessary work order or object ID.
- In the graphical object structure select the 
	operation for which you want to define a successor.
- Click the Dependencies tab and then 
	click the Successors sub tab.
- Create a new record (F5).
- In the Successor Operation No field, enter 
	the operation that is to be the successor. Use the List of Values to select 
	a valid value.
- Save the information (F12).
Use this procedure to define a successor for a certain 
work order:
	- Open the Work Order Execution Logic 
	window and query (F3) for the necessary work order or object ID.
- In the graphical object structure select the work 
	order for which you want to define a successor.
- Click the Dependencies tab and then 
	click the Successors sub tab.
- Create a new record (F5).
- In the Successor WO Number field, enter the 
	operation that is to be the successor. Use the List of Values to select a 
	valid value.
- Save the information (F12).
Predecessors 
dialog box
To define dependencies between operations, follow the 
procedure described in 
Define Predecessor Relationships.
To define dependencies between work orders, follow the 
procedure described in 
Define Predecessor Relationships for Work Orders.