Connect Operation to Tools and Facilities
Explanation
This activity is used to define the
operation that is planned to utilize the tools and facilities.
This activity is a must if the operation is to be scheduled using IFS/CBS.
Prerequisites
	- The work order operations must be defined
prior to connecting required tools and facilities to operations. The connection between a tool or facility and an operation 
  is mandatory if the standard job will be connected to a work order that 
belongs to a VIM serial object. 
- If IFS/CBS is used to schedule the operation a tool and facility will be 
	assigned and the value in the From Date/Time and To Date/Time 
	fields of the tools 
	and facilities line will be be updated to that of the 
	operation line when the status of the work order is changed to Prepared.
System Effects
None
Window
Prepare Work Order
Work Order Execution 
Logic
Related Window Descriptions
Prepare Work Order 
Prepare Work Order/Tools and Facilities  
Work Order Execution Logic 
Work Order Execution Logic/Tools 
and Facilities   
Procedure
Use the following procedure to connect operation to tools
and facilities:
  - Select the 
	Tools and Facilities tab and use the New
    function.
  
- In the Tool/Facility Type field,
    use the List of Values to enter a tool or facility type. It is also possible to
    only enter a tool or facility ID. If that is the case use the List of Values in the Tool/Facility
    ID field and enter a tool or facility ID.
  
- In the Quantity field,
    specify the quantity of the tool or facility that will be used for the
    work order (if known).
     
  
- In the Planned Hour 
    field, specify the number of planned (if known).
  
- In the Operation No field, use the List of Values to select
    an operation line number. Save the information.