Connect Work Order to Project Activity
Explanation
This activity is used to connect a work order to an existing project
activity. You will only be able to connect the work orders that do not
contain any cost transactions, such as material, tools and facilities, operations
and so on.
Prerequisites
  - IFS/Project must have been installed along with IFS/Work Order.
- All the necessary basic data required for a work order must be performed
    in order for the Connect To Activity right mouse button option to be
    enabled (right-click and point to Project Connections).
System Effects
	- The work order will be connected to the
specified project activity as a manually connected object. Right-click and click
	Project Activity Info to view a summary of the project activity. 
	
- The work order will also be updated
with the project's pre-posting when the project has been approved, and it will appear as a connection
on the Project
Info/Connections  tab in IFS/Project.
-  If the work order belongs to a structure then the project 
	connection will be performed for all work orders within that structure.
Window
Prepare
Work Order 
Related Window Descriptions
Prepare Work Order
Prepare Work Order/General
Historical Work Orders 
Historical Work Order
Historical Work Order/General
Procedure
  - Open the 
	Prepare Work Order  window, and click the 
	General
    tab.
- Create a new work order (F5), or query for an existing one (F3).
- Right-click anywhere on the window, point to Project Connections,
    and click Connect to Activity. The 
	Connect to Activity
    dialog box appears.
- Enter the program ID, project ID, sub project ID, and the
  relevant activity sequence. Click List to select the appropriate
  values.
- Click OK. If the work order is successfully connected to a project
    activity, the Project Connected check box on the 
	General tab will be selected.