Create and Connect Work Order (Graphical)
Explanation
Use this activity to create a new work order and connect
it to a superior work order. 
Prerequisites
The superior work order should be retrieved in
the 
Work Order Structure  window.
System Effects
As a result of this activity, a new work order is
created and included in a structure. All work orders connected to a superior
work order have to be
completed before the superior work order's status is changed to Finished.
Window
Prepare Work
Order
Related Window Descriptions
Prepare Work Order  
Graphical
Work Order Structure
Procedure
  - Open the 
	Prepare Work Order window
    and create a new record (F5) or query for an existing one (F3). Right-click
    and click Work Order Structure.
- In the 
	Work Order Structure  window, 
	select a work order for which you want to create a child work order, right-click and 
	then click Create WO.
- In the  Create Work Order under Parent  dialog box,
    enter a
    short description in the  New WO Directive  field.
- Enter values in the  Planned Start and  Planned
    Finish fields.
- In the Maint.Org. field, enter a suitable
    maintenance organization that would be responsible for the work order. Click
    List to select a suitable value.
- Enter a customer in the Customer field
    if you are using IFS/Service Management. Click List to select a
    suitable value.
- Click OK.
Note: You can also open 
Work
Order Structure from IFS/Navigator. The left part of the window shows
all work orders that are included in structures.