Create Revenue Transactions for Maintenance Order
Explanation
This activity is used to create revenue transactions on work orders that are created for a maintenance order. When the maintenance order 
is released (in IFS/Vehicle Information Management), work orders are created (in 
IFS/Work Order Management) in different ways, depending on the distribution type 
on the maintenance order. These work 
orders will have the VIM connection type and contain all operations 
(instructions and subtasks), materials, tools-and-facilities etc. that are 
transferred from the maintenance order.
This activity can be performed multiple times, and for each time it is 
performed the system will check the prerequisites and create or recreate revenue 
transactions for the tasks that meet the prerequisites.
Prerequisites
To create revenue transactions for the tasks on the 
maintenance order, the following must be completed:
	- A customer must be registered on the maintenance 
	order.
- The task must be in the Work Done status.
- If a service quotation is connected to the 
	maintenance order to which the task belongs, the service quotation must be 
	in the Accepted status.
- If a service quotation is connected to the task, 
	this quotation must be in the Accepted status, and the task must be accepted.
- The work order must be created for the task.
- All work order cost transactions originating from 
	the task must be in the Authorized status.
- There must not already exist a revenue transaction 
	for the tasks that have been authorized.
System Effects
If the task is connected to a service quotation that is 
in the Accepted status, and the task itself is accepted:
	- The cost transaction lines for the task are set to the Not 
	Invoiceable status and the price from the quotation will be used for 
	invoicing.
- A revenue posting line is created with a document text with information 
	from which quotation it originates, the task and task description from the 
	maintenance order and the text entered in the Work Carried Out field 
	on the maintenance task.
- The revenue posting line will be created in a status that makes it valid 
	for authorization, which needs to be done before transfer to the customer order.
If the task is not connected to a service quotation but 
is connected to a maintenance order that is connected to a service quotation in 
the Accepted status, and if this task is registered as a non routine and 
the emergent work percentage on the quotation is not 0:
	- The cost transaction lines for the task are set to the Not 
	Invoiceable status.
- A revenue posting line is created, where the sales part is retrieved 
	from the sales part defined as the one for emergent work for the site.
- The revenue posting line is created with a document text 
	with information that it originates from emergent work on a quotation, the 
	task and task description from the maintenance order, and the text entered 
	in the Work Carried Out field on the maintenance task. 
- The revenue posting line will be created in a status that makes it valid 
	for authorization, which needs to be done before transfer to the customer 
	order.
- The sales part price is the sum of all prices 
	for the corresponding cost transactions for the task.
If the task is not connected to a service quotation but is connected to a 
maintenance order that is connected to a service quotation in the Accepted 
status, and if this task is not a non routine task, it is considered as scope 
that needs to be done in conjunction with the other work, but that cannot be 
invoiced. For such instances,
	- The cost transaction lines for the task are set to the Not 
	Invoiceable status.
- No revenue line is created.
If the task and the maintenance order to which it 
belongs is not connected to a service quotation, but a customer is registered on 
the maintenance order, it is considered as if the work will be invoiced to that 
customer. For such instances,
	- The cost transaction lines are set to the Not 
	Invoiceable status.
- A revenue posting line is created, where the sales part is retrieved 
	from the sales part defined as the one for emergent work for the site.
- The revenue posting line is created with a document text 
	with information from the task and task description from the maintenance 
	order, and the text entered in the Work Carried Out field on the 
	maintenance task. 
- The revenue posting line will be created in a status that makes it valid 
	for authorization, which needs to be done before transfer to the customer 
	order.
- The sales part price is the sum of all prices 
	for the corresponding cost transactions for the task.
If the distribution type on the maintenance order is set to Execution 
Logic Structure, all revenue lines will be created on the top work order in 
the work order structure. In all other cases, the revenue posting lines will be 
created on the work order for the task.
Window
Report In 
Work Order
Related Window Descriptions
Report In Work Order 
Report In Work Order/Postings 
Create Revenue Transactions for 
Maintenance Order - Dialog Box
Procedure
	- Open the Report In Work Order window 
	and query (F3) for the necessary work order.
- Click the Postings tab.
- Right-click and then click Create Revenue 
	Transactions for Maintenance Order. The Create Revenue 
	Transactions for Maintenance Order dialog box opens.
- Click OK.