Define Activity Type
Explanation
This activity is used to define activity types for 
Scheduling. To do this, the work types defined in IFS/Basic Data for 
Maintenance should be set up as scheduling activity types. The following 
scheduling information can be defined per activity type:
	- A default execution time for the work orders using 
	the work type. This value will be inherited by work orders for which an 
	execution time has not been defined and where the total execution time for 
	the connected operations is set to zero.
- A scheduling value per hour. This value will be 
	used in the activity base value calculation, i.e., the base value per hour 
	will be multiplied by the default duration and any relevant weightings, to set the base value for the 
	activity. Note: If the base value is set to zero, work orders using 
	the work type will not be scheduled in the Scheduling Engine.
- A default buffer time in hours and/or as a 
	percentage. The default buffer time is added to the execution time when 
	calculating the available time window, for work orders for which a 
	requested finish, SLA req finish or planned finish date is specified. The buffer 
	time is calculated to the highest value of the buffer time or buffer 
	percentage multiplied by the activity duration.
- The duration in hours for the default primary scheduling 
	type and/or default secondary scheduling type for the work orders using the work 
	type. If a work order is missing the primary or secondary scheduling type, the 
	default primary or secondary scheduling type which is defined per dataset will be 
	assigned to the work order. For such work orders, or when the scheduling type 
	duration cannot be calculated from the current work order dates, the 
	duration entered for the default primary scheduling type or the default secondary 
	scheduling type 
	will be used to calculate the duration of the primary or secondary SLA 
	window.
- The Availabilities defined in Basic data for scheduling/Appointment can 
	be connected to a work type, so that the default data required in 
	Appointment booking functionality is taken from this Availability.   
Prerequisites
	- The company must have been set up in 
	IFS/Enterprise.
- Work types must have been defined in the Work Order and PM Basic 
	Data/Work Types tab.
System Effects
As a result of this activity, the activity types which 
are to be scheduled are defined.
Window
Basic Data for 
Scheduling
Related Window Descriptions
Basic Data for Scheduling 
Basic Data for Scheduling/Work Order
Basic Data for Scheduling/Work 
Order/Activity Type 
Procedure
	- Open the Basic Data for Scheduling 
	window.
- Click the Work Order tab and then 
	click the Activity Type sub tab.
- Verify that the correct company is in use. If not, 
	right-click and click Change Company to change the company.
- Create a new record (F5).
- In the Work Type field, enter the work type 
	that is to be used as an activity type. Use the List of Values to select a 
	valid value.
- In the Duration (Hours) field, enter the default duration in 
	hours for work orders with the selected work type.
- In the Base Value per Hour field, enter the 
	scheduling value for the activity. If a value is not entered in the field, when saving, 1000 is 
	entered by default. 
- In the Buffer Time (Hours) field, enter the 
	default buffer time in hours. Entering a value in this field is optional.
- In the Buffer Time (%) field, enter the 
	default buffer time as a percentage. Entering a value in this field is 
	optional.
- In the Scheduling Type (Primary) Duration Hours 
	field, enter the duration in hours for the default primary scheduling type.
- In the Scheduling Type (Secondary) Duration Hours 
	field, enter the duration in hours for the default secondary scheduling type.
- In the Availability field, enter an Availability id already 
	defined in Scheduling Basic Data/Appointment. Entering a value in this field 
	is mandatory.
- In the Displaceable Until Days field, enter the number of days 
	prior to the Primary Scheduling Type End where the Work Order may be 
	displaced by Appointments.
 (E.g. If Displaceable Until Days has been set to 20 days, then the Work 
	Order may be displaced until 20 days are remaining to the Primary Scheduling 
	Type End. If Displaceable Until Days has not been set the Work Order will 
	not be displaced.)
- Save the information (F12).