This activity is used to define the shift utilization. Shift utilization is a template that can be applied for resource types or resources. It is used to define the utilization percentage in a shift that a resource can be utilized. It should be given in a percentage value.
When setting the utilization on a shift the 
following logic is used:
1. If utilization per shift has been defined in the Shift Utilization 
then this will be the utilization that will be applied to the shifts for the 
Resource.
2. If utilization per shift has not been provided in the Shift Utilization 
then the Utilization defined in Resource will be set 
as default to all the shifts that belongs to the particular resource.
3. If utilization per resource has not been provided per resource then the 
Utilization defined in Resource Type will be set as 
default to all the shifts that belongs to resources of this resource type.
If user has defined a Shift Utilization ID on the resource or the resource type, then the following logic should be applied.
Template Example:
This is how the template will be used for a scheduling period of 8 days. Below table shows the utilization (%) defined for each day.
| Start Day | Utilization (%) | 
| 1 | |
| 2 | 0 | 
| 3 | 80 | 
| 5 | 60 | 
Day 1 = No value is given for the utilization (utilization % defined in 
Utilization in Resource/Resource Type is used)
Day 2 = 0%
Day 3 = 80%
Day 4 = Not defined in the shift (utilization % defined for the prior day is 
used i.e. 80% utilization)
Day 5 = 60%
Day 6 = 60%  (Not defined in the shift. The utilization % defined 
for the 
prior day is used i.e. 60% utilization)
Day 7 = 60%  (Not defined in the shift. The utilization % defined for 
day 5 is used. Therefore the utilization is 60%)
Day 8 = 60%  (Not defined in the shift. The utilization % defined for 
day 5 is used. Therefore the utilization is 60%)
Note:
The time interval that is used for the scheduling period is determined in the
Scheduling Dataset window. The scheduling period is the total 
number of days defined in Scheduling Working Days 
and  Appointment Work Days in accordance with the calendar defined for the 
dataset. 
For instance, if the Scheduling Working Days 
is set to 7 and  Appointment Work Days is set to 5 this will make a 
scheduling period of 12 working days (Calendar 
defines the working days). 
N/A
As a result of this activity, shift utilizations for a company are defined. Shift utilizations can be connected to resources and resource types.
Scheduling Basic Data  
Scheduling Basic Data/Shift 
Utilization 
Scheduling Basic Data/Resource 
Scheduling Basic Data/Resource 
Type