Disconnect Work Order from Project Activity
Explanation
This activity is used to disconnect a work order or a 
work order structure from a project activity.
A work order can be disconnected only if it does not contain any
cost transactions such as material, tools and facilities, operations, and so on. 
Prerequisites
  - IFS/Project must have been installed along with IFS/Work Order.
- A work order must have been manually connected to a project activity. 
System Effects
As a result of this activity, the work order will be
disconnected from the project activity, and it will not appear as a connection on the
Project
Navigator/Connections  tab in IFS/Project.
Window
Prepare
Work Order 
Related Window Descriptions
Prepare Work Order
Prepare Work Order/General
Historical Work Orders 
Historical Work Order/General
Procedure
  - Open the  
	Prepare Work Order window.
- Query for the connected work order (F3).
- Right-click anywhere on the window, point to Project Connections,
    and click Disconnect from Activity. 
- If the selected work order is connected to a 
	structure, an information message appears. Click Yes if you also want 
	to disconnect all work orders below the selected work order in the 
	structure. When you click Yes, the Project Connected check box 
	in the General tab will be cleared for the selected work order 
	and all work orders below it. When you click No, the check box will 
	only be cleared for the selected work order.