Move Operations between Work Orders
Explanation
This activity is used to move an operation from one 
work order to another within the Execution Logic Structure (ELS).
Prerequisites
	- The operation must have been defined.
- The work order to which the operation is to be 
	moved must exist in the ELS.
- The status of both the source and destination work 
	order cannot be higher than Under Preparation.
- Dependencies cannot exist on the operation.
System Effects
As a result of this activity, the operation is moved to 
another work order. 
Window
Work Order Execution Logic 
Related Window Descriptions
Work Order Execution Logic 
Structure 
Work Order Execution Logic Structure/Gantt
Procedure
Using the graphical object structure:
	- Open the Work Order Execution Logic 
	window.
- Query (F3) for the desired work order or object 
	ID.
- In the graphical object structure, select the 
	operation you want moved, right-click, and then click Move Operation. 
	The Move Operation dialog box opens. 
- In the editable WO No field, use the List 
	of Values to select the work order to which the operation is to be moved.
- Click OK.
Using the Gantt chart:
	- Open the Work Order Execution Logic 
	window and query (F3) for the desired work order or object ID.
- Click the Gantt chart. 
- In the chart, the operation can be moved manually 
	or by using the Move Operation dialog box.
- To move an operation manually, select the activity 
	bar for the operation, and then drag it to the new work order. Save your changes (F12).
- To access the Move Operation dialog 
	box, select the activity bar for the operation, right-click, and then click
	Move Operation. 
- In the editable WO No field, use the List 
	of Values to select the work order to which the operation is to be moved.
- Click OK.