Perform Condition Measurements
Explanation
This activity is used to record condition measurements 
on a work order operation. During execution of a scheduled maintenance it is 
possible to find abnormalities, such as, measurements that are outside the defined 
condition limits. When such measurements are found, you can use the 
functionality described in this activity to record the new measurements and 
initiate corrective action. When a measure value that is outside any of the 
defined condition limits is recorded, a maintenance task is created and added 
automatically to the work package (maintenance order) for the ongoing work 
scope.  
Note: If condition measurement requirements exist on an 
operation these measurements must be performed before the operation can be 
completed.
Prerequisites
	- The work order operation must exist in either the
	Released or Started status.
- Condition measurement requirements must be defined 
	on the operation, i.e., the Condition Measurement Required check box 
	must be selected on the operation line.
- Condition limits must have been defined for the 
	serial connected to the work order operation.
System Effects
	- Condition measurements are recorded on the work 
	order operation. This information can be viewed in the Condition Meas. 
	subtab.
- The Condition Measurement Performed check 
	box will be selected on the operation line.
- If the measurement is outside the defined limits, 
	a maintenance task is generated for it. The task will be added automatically 
	to the maintenance order for the ongoing work scope.
- The condition measurements reported on the operation will be transferred 
automatically to IFS/Vehicle Information Management and a history record will be 
generated.
Window
Prepare Work Order 
Report In Work Order
Work Order Execution 
Logic    
Related Window Descriptions
Prepare Work Order 
Prepare Work Order/Operations 
Report In Work Order 
Report In Work Order/Operations 
Work Order Execution Logic 
Work Order Execution Logic/Operations  
Procedure
	- Open the Prepare Work Order window 
	and query (F3) for the necessary work order.
- Click the Operations tab.
- Right-click and then click Perform Condition 
	Measurement. The Perform Condition Measurement dialog box 
	opens.
- In the Measure Value field, enter the 
	measured value of the condition. Note that the previous measurement appears 
	by default and must be overwritten with the new measure value.
- In the Measure Date field, enter the date 
	on which the condition measurement was completed. The default value is set 
	to today's date (i.e., system date) but can be changed.
- Click OK.
- Click the Condition Meas. subtab to 
	view information on the condition measurement that was entered. 
Note: It is also possible to report condition 
measurements on an operation in the Report In Work Order/Operations 
tab and the Work Order Execution Logic/Operations tab.