Replan and Reschedule Activities
Explanation
Use this activity to replan and reschedule the 
activities (i.e., operation tool-and-facility lines) that have allocations.
Prerequisites
Resources must be allocated to activities in the respective 
windows.
System Effects
As a result of this activity, the operation and/or 
tool-and-facility line will be replanned and rescheduled.
Window
Resource Allocation 
Gantt
Related Window Descriptions
Resource Allocation Gantt
Procedure
  - Open the 
	Resource Allocation Gantt window 
	and perform a search.
- Filter the results using the fields in the 
	Filters area if required.
- To move the allocations, select the horizontal 
	bar, drag and drop to the required time slot.
- To change the duration of the allocation, resize 
	the bar or double-click on the bar and enter new start and end dates and 
	times.
- Save the information (F12).