Report Work as Done
Explanation
This activity is used in order to indicate that work described in the work order 
has been completed. 
Prerequisites
To perform this activity, a work order in the Started status must exist.
System Effects
	- The work order receives the Work Done status. 
- As soon 
	as the work order receives the Work Done status, the work order is no 
	longer available for the contractor to access using the Business-to-Business 
	interface. 
Window
N/A
Related Page Descriptions
Active Work Orders Portlet 
Report in Work Order
Procedure
	- Click on the Report In link in the Active Work Orders 
	portlet. The Report in Work Order page is opened.
- Click Work Done on the Actions menu.