Reschedule Operations
Explanation
This activity is used to reschedule the operation lines of a 
work order. You can perform this activity on the 
Prepare Work 
Order/Prepare tab, the 
Prepare Work Order/Operations tab 
or the  Work Order Execution Logic/Operations tab. 
Note: The steps related to time-shifting an operation 
and its successors can 
be performed on the Prepare Work Order/Operations 
tab
or the Work Order 
Execution Logic/Operations 
tab.
Prerequisites
	- Operation lines must have been defined and predecessor 
	relationships (optional) established.
- If you want to reschedule all the operation lines entered 
on a work order, the start and/or end dates for the work order must have been entered on the 
	Prepare Work 
Order/Prepare
	tab.
- If you want to reschedule individual operation lines, 
	the start and/or end dates must have been specified for the 
	individual operation lines you want to reschedule.
- IFS Human Resources must have been installed if you want 
	to use the HR (Human Resource) employee schedule.  
System Effects
As a result of this activity operation lines will be rescheduled based on 
your preferences.
Window
Prepare 
Work Order 
 
Work Order Execution 
Logic 
Related Window Descriptions
Prepare 
Work Order 
Prepare Work 
Order/Operations 
Prepare Work Order/Jobs 
Work Order Execution Logic 
Work Order Execution 
Logic/Operations 
Procedure
To reschedule an operation:
	- Open the Prepare Work Order window 
    or the  Work Order Execution Logic window
	and click the Operations tab.
- Define predecessor relationships among the 
	operation lines if required. Also make sure that the relevant operation 
	lines contain the start date (at least). 
- Select the operation you want to reschedule, right-click and
      then click 
	Reschedule Operations. The Reschedule 
	Work Order Operations dialog 
	box opens.
- To reschedule start and end times on the operations, select the Operation check box.
- If the operation line is connected to one or more 
	tool-and-facility lines and they should be rescheduled, select the Tools and Facilities check box so 
	that the dates of the tool and facility line will be changed accordingly.
- If you need to optimize the duration of the 
    operations, select the Compress Durations check box so that the duration 
    of the operation is reduced to the minimum possible.
- If employees have been allocated to 
    operations and available time slots can be found,
 select the Employee 
    Allocations check box.
- If the employee schedules should be considered so 
    that only the scheduled time should be used, select the Include Schedule 
    check box. Next, verify that the requested start date 
	and earliest end date is correct or modify it as required. Note: 
	These dates are used 
	to retrieve the employee schedule from IFS Human Resources, if installed. If 
	not the schedule of the maintenance organization to which the employee 
	belongs is retrieved.
- Click OK.  
To reschedule all the operation lines on a work order:
	- Open the Prepare Work Order window.
- Right-click on the window header or the 
	General tab and click Reschedule Operations.
- Perform steps 4 to 9 above. 
To move an operation (time shifting) and its successors:
	- Open the Prepare Work Order 
	window 
	or the Work Order Execution Logic window
	and click the Operations 
	tab.
- Select the operation you want to move, 
	right-click and then click Change Planned Start.
- Specify the new start date and time in the New 
	Start Time field.
- Click OK.