Reset Status of Purchase Requisition Header or Line to Planned
Explanation
This activity is used to change the status of a
released purchase requisition or a requisition line to Planned.
Prerequisites
The purchase requisition or requisition line must
    have Released status.
System Effects
As a result of this activity, the purchase
requisition or requisition line is demoted from Released to Planned status.
Window
Prepare Work Order
Related Window Descriptions
Prepare Work Order 
Prepare
Work Order/Requisitions 
Prepare
Work Order/Requisitions/Part Requisition Lines 
Prepare
Work Order/Requisitions/No Part
Requisition Lines 
Prepare Work Order/Requisitions/Rental Part
Requisition Lines
Procedure
Use the following procedure to demote a requisition
line to Planned: 
  - Open the 
	Prepare Work Order window and
    query for the applicable work order number.
- Click the 
	Requisitions tab and query
    for the applicable purchase requisition number.
- Click the 
	 Part Requisition Lines, 
	 No-Part Requisition Lines 
	or the Rental Part Requisition Lines tab and select the requisition line to be demoted. If required, you can also
    select several lines.
- Right-click and then click Change to Planned. The status
    of the line is
    changed back to Planned.
Use the following procedure to demote an entire
requisition to Planned: 
  - Click in the header of the 
	Requisitions
    tab.
- Right-click and then click Change to Planned. The status
    of the header and all lines is
    changed to Planned.