View Calculated Progress
Explanation
This activity is used to graphically view the work progress of work orders in 
the work order structure that is created for an Execution Logic Structure (ELS). 
Once the progress of work is calculated on a work order, the activity bar for 
the work order in the Gantt will be updated to show the progress. 
Prerequisites
To perform this activity, progress must have been reported on the work order.
System Effects
As a result of this activity, it is possible to graphically view how much of 
the work has been completed.
Window
Work Order 
Execution Logic 
Related Window Descriptions
Work Order Execution Logic 
Work Order Execution Logic/Gantt 
Procedure
	- Open the Work Order Execution Logic window and query (F3) 
	for the necessary work order.
- In the graphical object structure, select the required structure level.
- Click the Gantt tab.
- Observe the progress shown in the relevant activity bars. Progress is 
	shown by a Black-and-White striped bar within the activity bar.
- The actual value of progress is shown in the tool-tip for the activity 
	bar if the Progress (%) check box is selected (in the Tool Tip 
	Properties dialog box).