Use this window to display activity information in the corresponding tabs available.
The window can also be accessed from Sub Projects or Activities windows. If more than one subproject or activity has been selected from either of these windows, the activities will be available in the Project combo box. This enables you to work with activity information from different projects.
For the description of each tab in the window, follow the appropriate link: General, Cost, Revenue, Hours, Sub Project, Tasks, Connections, Demand, Supply, Resources, Planning, Estimate.
If IFS/Preventive and Corrective Maintenance is used together with IFS/Project, the tab Work Orders will also be available.
	Initiate Project
	
	Establish Project
  Plan
	
	Approve Project
	
	Complete Project
	
	Close Project
	
	Restart Project
	Execute 
Activity
Insert
      Activities
	Connect
      Document to Activity
Copy Activity
	Cancel Activity
	Release
      Activity
	Complete
      Activity
Close Activity
	Reopen Activity
	Delete Activity
	Evaluate Cost, Hours, Revenue and Progress from Connected Objects