Project Periodical Cost Graph/Graph
Usage
Use this tab to view graphically and compare the budget and the actual cost/revenue spread within 
the project life span.
The following costs lines will be depicted:
	- Cost: EAC Cumulative: The graph of the EAC costs spread in to future 
	accounting periods.  
- Cost: Estimate At Completion (EAC): The total EAC for the selected forecast version. 
- Cost: Budget At 
	Completion (BAC): The total budget value of the forecast version set as Active 
	Budget.
- Cost: Budget Cumulative: The graph of the budget costs spread in to each 
	accounting period.
- Cost: Incurred Cumulative: The graph shows the sum of the committed cost + 
	used cost incurred in each 
	accounting period up until the Cut-Off Period. 
- Cost: Earned Value: The Budget * Progress for the accounting period. A 
	prerequisite for earned value to be shown is a forecast type with periodic 
	review. 
Also the following revenue lines will be depicted:
	- Revenue: EAC Cumulative: The graph of the EAC 
	revenue spread in to future 
	accounting periods.  
- Revenue: Estimate At Completion (EAC): The total EAC for the selected forecast version. 
- Revenue: Budget At Completion (BAC): The total budget value of the forecast version set as Active 
	Budget.
- Revenue: Budget Cumulative: The graph of the budget 
	revenue spread in to each 
	accounting period.
- Revenue: Incurred Cumulative: The graph shows the sum of the preliminary 
	revenue + posted revenue incurred in each 
	accounting period up until the Cut-Off Period.
In addition to the cost and revenue line graphs, the forecast cut-off period will also be displayed. 
If Live View snapshot functionality is used the 
incurred costs/revenue cannot be spread into specific periods. The cumulative incurred 
cost/revenue in this case will be plotted on the cut-off period line.